Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24PL0046

DPWH infrastructure contract
Contract ID:
24PL0046
Fingerprint:
2e6fde1965efc1…6f17053ecf Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 24, 2024 (2 yrs 4 mo ago) · Target/actual end Nov 29, 2024
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF KINAMA/ BULBUL - PANABANG/ MACUTAY/ LIWAN - CALAOCAN/ CALAMINOS RNSAT, IN BARANGA
Category:
Roads
Implementing office:
DPWH Lower Kalinga DEO · Cordillera Administrative Region
Contractor:
ADEB'S CONSTRUCTION · DPWH contractor code 30793
Contract amount:
₱7,913,449.88 (₱7.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
5888cbb78c6a…Jun 10, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LOWER KALINGA DEO₱7,913,449.88

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26BF0037Aug 3, 2026ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - LAGUINDAY PARALLEL BR. ALONG SANTIAGO-TUGUEGARAO RD, RIZAL KALINGAOn-Going₱56.1M
25BF0104Oct 13, 2025RAINWATER COLLECTOR SYSTEM 1. VICTORIA ELEMENTARY SCHOOL, AURORA, ISABELA 2. BURGOS NATIONAL HIGH SCHOOL, BURGOS, ISABELA 3. HARANA ELEMENTARY SCHOOL, LUNA, ISABELA 4. BIMONTON INTEGRATED SCHOOL, MALLIG, ISABELA 5. MANANO ELEMENTARY SCHOOL MAIN, MALLIG,On-Going₱2.5M
25BF0068Aug 6, 2025OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, UPPER CHICO RIVER IRRIGATION SYSTEM, QUEZON, ISABELACompleted₱14.0M
25BF0089Aug 4, 2025CONSTRUCTION OF SCHOOL BUILDING, MINAGBAG INTEGRATED SCHOOL, QUEZON, ISABELACompleted₱4.8M
25BF0076Jul 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN JUAN, QUEZON, ISABELACompleted₱5.8M
25BF0078Jul 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BRGY. SAMONTE, QUEZON, ISABELACompleted₱9.6M
25BF0049Jun 30, 2025COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY TUROD, QUEZON, ISABELAOn-Going₱4.8M
25BF0029Jun 16, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BARANGAY SAMONTE, QUEZON, ISABELAOn-Going₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.