Project 25A00113
DPWH infrastructure contract
Contract ID:
25A00113
Fingerprint:
0b47893e6dfa7e…22c57619df Verified
Status:
On-Going
Physical progress:
80.1%
Timeline:
Start Feb 21, 2025 (1 yr 8 mo ago)
Description:
CONSTRUCTION OF MISSING LINKS/ NEW ROADS - CERVANTES - QUIRINO (ILOCOS SUR) - ABRA ROAD, ILOCOS SUR (PACKAGE 5)
Category:
Roads
Implementing office:
DPWH Region I · Region I
Contractor:
A.I.P. CONSTRUCTION · DPWH contractor code 32458
Contract amount:
₱93,629,026.69 (₱93.6M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 15d57ac7184b… | Feb 10, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION I | ₱93,629,026.69 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AD0017 | Mar 19, 2025 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - CERVANTES - QUIRINO RD - K0403+694 - K0403+1029 | Completed | ₱8.5M |
| 25A00021 | Feb 24, 2025 | CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA RIVER, UPSTREAM OF QUIRINO BRIDGE, QUIRINO, ILOCOS SUR | On-Going | ₱145.1M |
| 25A00022 | Feb 24, 2025 | CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA RIVER, DOWNSTREAM OF QUIRINO BRIDGE, QUIRINO, ILOCOS SUR | On-Going | ₱145.1M |
| 25A00170 | Feb 21, 2025 | CONSTRUCTION OF MISSING LINKS/ NEW ROADS, CERVANTES (ILOCOS SUR) - BESAO-SAGADA VIA LAYLAYA ROAD, ILOCOS SUR (PACKAGE 5) | On-Going | ₱93.6M |
| 25AD0035 | Feb 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, QUIRINO, ILOCOS SUR | Completed | ₱9.6M |
| 24PA0170 | Nov 6, 2024 | CONSTRUCTION OF MISSING LINKS / NEW ROADS, ABRA-CERVANTES RD, (JUNCTION TUBTUBA-DILONG SECTION), TUBO, ABRA | On-Going | ₱137.9M |
| 24PA0127 | Oct 31, 2024 | CONSTRUCTION OF MISSING LINKS / NEW ROADS, BESAO-TUBO (VIA TAMBOAN) ROAD, ABRA | On-Going | ₱137.6M |
| 24PA0171 | Oct 31, 2024 | CONSTRUCTION OF MISSING LINKS / NEW ROADS, ABRA-CERVANTES RD, (PALTING-LAMAG SECTION), TUBO, ABRA | On-Going | ₱138.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.