Project 25A00133
DPWH infrastructure contract
Contract ID:
25A00133
Fingerprint:
a77e1be481afe9…7feafa2569 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 25, 2025 (1 yr 8 mo ago) · Target/actual end Apr 22, 2025
Description:
BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY RIZAL, TUBAO, LA UNION
Category:
Flood Control and Drainage
Implementing office:
DPWH Region I · Region I
Contractor:
VILLAR GENERAL CONSTRUCTION & SUPPLIES · DPWH contractor code 22540
As listed: VILLAR GENERAL CONSTRUCTION AND SUPPLIES
Contract amount:
₱33,617,380.53 (₱33.6M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 344add75c0b8… | Feb 14, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION I | ₱33,617,380.53 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25A00500 | Jun 16, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ARINGAY RIVER BASIN, PACKAGE 3, BARANGAY ANDUYAN, TUBAO, LA UNION | On-Going | ₱57.6M |
| 25AF0097 | May 15, 2025 | CONST/MAINT. OF FLOOD MIT. STRUCTURES & DRAINAGE SYS. - CONST. OF FLOOD CONTROL STRUC. ALONG ARINGAY RIVER BASIN, TUBAO, LA UNION (SECTION 38) | Completed | ₱28.1M |
| 25AF0098 | May 15, 2025 | CONST/MAINT. OF FLOOD MIT. STRUC. & DRAINAGE SYS- CONST. OF FLOOD CONTROL STRUC. ALONG ARINGAY RIVER BASIN, TUBAO, LA UNION (SECTION 39) | Completed | ₱18.7M |
| 25AF0099 | May 15, 2025 | CONST/MAINT. OF FLOOD MIT. STRUCTURES & DRAINAGE SYS- CONST. OF FLOOD CONTROL STRUCTURES ALONG ARINGAY RIVER BASIN, TUBAO, LA UNION (SECTION 40) | Completed | ₱14.0M |
| 24A00673 | Apr 4, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, AGOO-BAGUIO CITY ROAD - K0244 + 605 - K0247 + 435 (PACKAGE 05) | Completed | ₱81.2M |
| 24A00674 | Apr 4, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, AGOO-BAGUIO CITY ROAD - K0247 + 435 - K0250 + 265 (PACKAGE 06) | Completed | ₱81.2M |
| 25AF0081 | Mar 26, 2025 | IMPROVEMENT OF FMR HALOG WEST, TUBAO, LA UNION | Completed | ₱19.9M |
| 25AF0002 | Mar 13, 2025 | REHAB/RECONST OF ROADS W/ SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - AGOO-BAGUIO ROAD - K0247+747 - K0247+794, TUBAO, LA UNION | Completed | ₱2.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.