Project 25A00507
DPWH infrastructure contract
Contract ID:
25A00507
Fingerprint:
4dd2607f1b15cc…a49992062a Verified
Status:
On-Going
Physical progress:
37.9%
Timeline:
Start Jun 3, 2025 (1 yr 5 mo ago)
Description:
BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, MANAOAG, PANGASINAN
Category:
GAA 2025 SSP
Implementing office:
DPWH Region I · Region I
Contractor:
MKM MARKETING · DPWH contractor code 15586
Contract amount:
₱4,795,740.41 (₱4.8M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AH0141 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING,BARANGAY POBLACION,MANAOAG, PANGASINAN | On-Going | ₱9.6M |
| 25AH0050 | Jun 11, 2025 | CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BARANGAY BAGUINAY,MANAOAG, PANGASINAN | Completed | ₱2.9M |
| 25AH0132 | Jun 11, 2025 | CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING AT BRGY. PARIAN,MANAOAG, PANGASINAN | Completed | ₱1.9M |
| 25AH0144 | Jun 11, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING(MANAOAG PILGRIMS ARENA)AT BRGY. POBLACION,MANAOAG,PANGASINAN | Completed | ₱4.8M |
| 25A00498 | May 27, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - CLUSTER III, CONSTRUCTION OF MULTI - PURPOSE BUILDING (1. BRGY POBLACION, BASISTA, PANGASINAN; 2. BRGY PUGARO, MANAOAG, PANGASINAN & 3. BRGY ANGATEL, URBIZTONDO, PANGASINAN) | On-Going | ₱28.8M |
| 25A00530 | May 27, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI PURPOSE BUILDING WITH SITE DEVELOPMENT, POBLACION, MANAOAG, PANGASINAN | On-Going | ₱19.2M |
| 25A00531 | May 27, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF LIGA NG BARANGAY MULTI - PURPOSE BUILDING, BARANGAY POBLACION, MANAOAG, PANGASINAN | On-Going | ₱9.6M |
| 25A00532 | May 27, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY POBLACION, MANAOAG, PANGASINAN | On-Going | ₱9.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.