Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25AF0051

DPWH infrastructure contract
Contract ID:
25AF0051
Fingerprint:
08a70d5d097379…4fccea4889 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 18, 2025 (1 yr 8 mo ago) · Target/actual end Jul 14, 2025
Description:
CONST/REHAB OF FLOOD MITI FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONST. OF FLOOD CONT. STRUC. ALONG ARINGAY RIVER BASIN, BRGY. SAN JUAN EAST, ARINGAY, LU
Category:
Flood Control and Drainage
Implementing office:
Contractor:
JWU CONSTRUCTION AND SUPPLY · DPWH contractor code 48659
Contract amount:
₱96,497,107.07 (₱96.5M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
2983cd099af3…Feb 12, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LA UNION 2ND ED₱96,497,107.07

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25A00526Jun 16, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ARINGAY RIVER BASIN, BARANGAY SANTA CECILLA, ARINGAY, LA UNIONOn-Going₱67.2M
25AF0100Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRIN RIVERS - CONST. OF FLOOD MIT STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION ARINGAY, LU (PHASE I)On-Going₱93.6M
25AF0101Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION ARINGAY, LU (PHASE 2)Completed₱93.6M
25AF0102Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION, ARINGAY, LU (PHASE 3)Completed₱93.5M
25AF0103Jun 11, 2025CONST/REHAB. OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN JUAN WEST, ARINGAY, LA UNIONCompleted₱93.6M
25AF0104Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASIN & PRINCIPAL RIVERS - CONST OF FOLOOD MIT. STRUCTURE ALONG ARINGAY, RIVER BASIN, BRGY. SAN SIMIN EAST, ARINGAY, LUOn-Going₱93.6M
25AF0105Jun 11, 2025CONST/REHAB OF FLOOD MIT FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LU (PHASE 1)On-Going₱93.6M
25AF0106Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LU (PHASE 2)On-Going₱93.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.