Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25AF0052

DPWH infrastructure contract
Contract ID:
25AF0052
Fingerprint:
b7a08312e12d6f…b600f7d229 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 18, 2025 (1 yr 8 mo ago) · Target/actual end Jun 30, 2025
Description:
CONST./MAINT. OF FLOOD MIT. STRUC. & DRAINAGE SYS. - CONST. OF FLOOD CONTROL STRUC. ALONG ARINGAY RIVER BASIN. BRGY. POBLACION, ARINGAY. LA UNION
Category:
Flood Control and Drainage
Implementing office:
Contractor:
JWU CONSTRUCTION AND SUPPLY · DPWH contractor code 48659
Contract amount:
₱96,497,916.51 (₱96.5M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
f411f31e1cd9…Feb 12, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LA UNION 2ND ED₱96,497,916.51

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25A00526Jun 16, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ARINGAY RIVER BASIN, BARANGAY SANTA CECILLA, ARINGAY, LA UNIONOn-Going₱67.2M
25AF0100Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRIN RIVERS - CONST. OF FLOOD MIT STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION ARINGAY, LU (PHASE I)On-Going₱93.6M
25AF0101Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION ARINGAY, LU (PHASE 2)Completed₱93.6M
25AF0102Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION, ARINGAY, LU (PHASE 3)Completed₱93.5M
25AF0103Jun 11, 2025CONST/REHAB. OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN JUAN WEST, ARINGAY, LA UNIONCompleted₱93.6M
25AF0104Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASIN & PRINCIPAL RIVERS - CONST OF FOLOOD MIT. STRUCTURE ALONG ARINGAY, RIVER BASIN, BRGY. SAN SIMIN EAST, ARINGAY, LUOn-Going₱93.6M
25AF0105Jun 11, 2025CONST/REHAB OF FLOOD MIT FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LU (PHASE 1)On-Going₱93.6M
25AF0106Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LU (PHASE 2)On-Going₱93.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.