Project 25AF0085
DPWH infrastructure contract
Contract ID:
25AF0085
Fingerprint:
8d65730cd471a1…07f04fd102 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 14, 2025 (1 yr 5 mo ago) · Target/actual end Jul 14, 2025
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. POBLACION SUR, CABA, LA UNION, PACKAGE 2
Category:
Flood Control and Drainage
Implementing office:
DPWH La Union 2nd DEO · Region I
Contractor:
Contract amount:
₱48,245,398.04 (₱48.2M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AF0117 | Jun 26, 2025 | CONSTRUCTION OF ROAD AT SITIO CENTRO, SAN FERMIN TO KANUBAT, SAN JOSE, CABA, LAUNION | Completed | ₱24.0M |
| 25AF0118 | Jun 26, 2025 | BIP-FLOOD MIT. STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BLDGS/FACI - CONST. OF FLOOD CONTROL STRUCTURE ALONG CABA RIVER BASIN, BRGY. GANA, CABA, LU | Completed | ₱24.0M |
| 25AF0088 | May 26, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. SAN JOSE, CABA, LA UNION PACKAGE 3 | Completed | ₱46.7M |
| 25AF0116 | May 15, 2025 | CONSTRUCTION OF ROAD AT SITIO CENTRO TO BARIKIR LIQUICIA, CABA,LA UNIPON | Completed | ₱23.8M |
| 25AF0084 | May 14, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. GANA, CABA, LA UNION PACKAGE 2, BRGY. GANA, CABA, LA UNION | Completed | ₱48.2M |
| 25AF0013 | Mar 13, 2025 | CONST/IMPRVMNT OF ACCESS RDS LDNG TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRA PROGRAM-TRIP) REHAB/IMPRVMNT OF ROAD LDNG TO TOURISM SITE - SAN CARLOS BEACH, CABA, LA UNION | Completed | ₱9.8M |
| 25AF0030 | Feb 18, 2025 | CONST. OF MULTI-PURPOSE BLDG (COVERED COURT), BRGY. GANA, CABA, LA UNION | Completed | ₱4.8M |
| 25AF0031 | Feb 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY POBLACION NORTE, CABA. LA UNION | Completed | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.