Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25AH0173

DPWH infrastructure contract
Contract ID:
25AH0173
Fingerprint:
92e77c0b8781aa…cbfb24f091 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 21, 2025 (1 yr 7 mo ago) · Target/actual end Jul 21, 2025
Description:
CONCRETING OF BRGY. MALABAGO-BRGY.ALITAYA SERVICE ROAD FMR,BRGY. MALABAGO,MANGALDAN,PANGASINAN
Category:
GAA 2025 DA FMR
Implementing office:
Contractor:
Contract amount:
₱14,447,354.45 (₱14.4M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AH0126Jun 11, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. BUENLAG,MANGALDAN,PANGASINANOn-Going₱2.9M
25AH0130Jun 11, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. GUESANG,MANGALDAN,PANGASINANOn-Going₱1.9M
25AH0131Jun 11, 2025REHABILITATION OF ROAD, BARANGAY AMANSABINA,MANGALDAN, PANGASINANCompleted₱4.8M
25AH0174Mar 21, 2025CONCRETING OF BRGY. SALAAN FMR,BRGY. SALAAN,MANGALDAN,PANGASINANCompleted₱14.5M
25AH0127Mar 20, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. POBLACION,MANGALDAN,PANGASINANCompleted₱1.9M
25A00286Feb 25, 2025WIDENING OF PERMANENT BRIDGES - EMBARCADERO BR. (B01329LZ) ALONG MANGALDAN-MANAOAG-BINALONAN RD (PHASE II)On-Going₱93.6M
25AH0077Feb 25, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, MANGALDAN, PANGASINANOn-Going₱3.9M
25A00165Feb 24, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - DAGUPAN-MANGALDAN DIVERSION ROAD, PANGASINANOn-Going₱58.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.