Project 25AJ0103
DPWH infrastructure contract
Contract ID:
25AJ0103
Fingerprint:
4e5ac164fc8d51…95a708b5aa Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 14, 2025 (1 yr 3 mo ago) · Target/actual end Nov 12, 2025
Description:
CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG AGNO RIVER, BARANGAY BONGATO EAST, BAYAMBANG, PANGASINAN
Category:
GAA 2025 SSP
Implementing office:
DPWH Pangasinan 4th DEO · Region I
Contractor:
BALLESTEROS CONSTRUCTION AND SUPPLY · DPWH contractor code 44614
Contract amount:
₱9,549,498.08 (₱9.5M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AJ0077 | Feb 12, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGNO RIVER, BONGATO WEST SECTION, BAYAMBANG, PANGASINAN | Completed | ₱33.2M |
| 24AJ0089 | May 16, 2024 | REHABILITATION OF ROAD, BRGY. BONGATO EAST, BAYAMBANG, PANGASINAN | Completed | ₱4.7M |
| 24AJ0097 | May 6, 2024 | 1. CONSTRUCTION OF FLOOD CONTROL STURCTURE ALONG AGNO RIVER, BONGATO WEST SECTION, BAYAMBANG, PANGASINAN 2. CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGNO RIVER, SAN VICENTE SECTION, BAYAMBANG, PANGASINAN 3. CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALO | Completed | ₱38.1M |
| 24AJ0066 | Apr 29, 2024 | REHABILITATION OF ROAD, BRGY. BONGATO WEST, BAYAMBANG, PANGASINAN | Completed | ₱14.3M |
| 24A00236 | Mar 15, 2024 | RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES, CALVO BR. (B02765LZ) ALONG CARMEN JCT - BAYAMBANG - MANAT RD | Completed | ₱93.1M |
| 23AJ0072 | May 12, 2023 | REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - CALVO BR. (B02765LZ) ALONG CARMEN JCT - BAYAMBANG - MANAT RD, BAYAMBANG, PANGASINAN | Completed | ₱5.8M |
| 19AJ0065 | Jul 5, 2019 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES-CALVO BR. (B02765LZ) ALONG CARMEN JCT.-BAYAMBANG-MANAT RD., BAYAMBANG, PANGASINAN | Completed | ₱13.6M |
| 19AI0051 | Jul 3, 2019 | CONSTRUCTION OF CACANDONGAN MULTI-PURPOSE BUILDING (COVERED COURT), CACANDONGAN, BAUTISTA, PANGASINA | Completed | ₱1.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.