Project 25BE0085
DPWH infrastructure contract
Contract ID:
25BE0085
Fingerprint:
b1c576e5dd698b…eeb1654d6c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 19, 2025 (1 yr 4 mo ago) · Target/actual end Jan 1, 2026
Description:
CONCRETING OF BRGY. PILIG ALTO FMR, BRGY. PILIG ALTO, CABAGAN, ISABELA
Category:
GAA 2025 DA FMR
Implementing office:
DPWH Isabela 1st DEO · Region II
Contractor:
DRAGON TWELVE BUILDERS AND CONSTRUCTION SUPPLY · DPWH contractor code 39808
As listed: DRAGON TWELVE BUILDERS & CONSTRUCTION SUPPLY
Contract amount:
₱19,302,954.80 (₱19.3M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BE0168 | Jun 17, 2026 | CONSTRUCTION OF CLASSROOMS, CANDANUM INTEGRATED SCHOOL, CABAGAN, ISABELA | On-Going | ₱28.5M |
| 25BE0143 | Jan 22, 2026 | CONCRETING OF SITIO PELO, BRGY. CANSAN FMR, BRGY. CANSAN, CABAGAN, ISABELA | On-Going | ₱14.5M |
| 25BE0131 | Sep 16, 2025 | CONSTRUCTION OF SCHOOL BUILDING, CUBAG INTEGRATED SCHOOL, BARANGAY CUBAG, CABAGAN, ISABELA | Completed | ₱19.3M |
| 24BE0183 | Aug 20, 2025 | CONSTRUCTION OF SEWAGE TREATMENT PLANT, MILAGROS ALBANO DISTRICT HOSPITAL, CABAGAN, ISABELA BARANGAY NGARAG, CABAGAN, ISABELA | On-Going | ₱28.1M |
| 25BE0078 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY AGGUB, CABAGAN, ISABELA | On-Going | ₱9.6M |
| 25BE0082 | Jul 14, 2025 | CONCRETING OF MALASI-SAN ANTONIO FMR, BRGY. SITIO MALASI, BRGY. SAN ANTONIO, CABAGAN, ISABELA | On-Going | ₱14.5M |
| 25BE0089 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG CAGAYAN | On-Going | ₱140.3M |
| 25BE0090 | Jul 14, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTUR | On-Going | ₱93.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.