Project 25BE0091
DPWH infrastructure contract
Contract ID:
25BE0091
Fingerprint:
a6d2e701e7b420…19ff99ebe2 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Jun 19, 2025 (1 yr 4 mo ago)
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, PHASE 5, BARANGAY MALA
Category:
GAA 2025 SSP
Implementing office:
DPWH Isabela 1st DEO · Region II
Contractor:
DRAGON TWELVE BUILDERS AND CONSTRUCTION SUPPLY · DPWH contractor code 39808
As listed: DRAGON TWELVE BUILDERS & CONSTRUCTION SUPPLY
Contract amount:
₱38,411,925.20 (₱38.4M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BE0084 | Jul 14, 2025 | CONCRETING OF BUBUG FMR (PHASE I), BRGY. BUBUG, STO. TOMAS, ISABELA | On-Going | ₱14.5M |
| 25BE0109 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SUPPLY SYSTEM AT BARANGAY BALELLENG, SANTO TOMAS, ISABELA | On-Going | ₱4.8M |
| 25BE0128 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES -CONSTRUCTION OF SLOPE PROTECTION AND CROSS DRAIN ALONG BAGABAG CREEK, STO. TOMAS, ISABE | Completed | ₱14.4M |
| 25BE0024 | Feb 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF CONCRETE ROAD AT BARANGAY | Completed | ₱14.7M |
| 24BE0149 | Dec 11, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD ALONG BARANGAY BUBUG | On-Going | ₱96.5M |
| 24BE0146 | Sep 5, 2024 | CONCRETING OF BRGY. BARUMBONG FMR, BRGY. BARUMBONG, STO. TOMAS, ISABELA | On-Going | ₱17.4M |
| 24BE0091 | Jun 13, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR /STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF BARANGAY BUBUG-SANTO TOMAS-QUEZON ROAD, SANTO | On-Going | ₱29.7M |
| 24BE0071 | May 28, 2024 | CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN BIGA INTEGRATED SCHOOL, BRGY. BIGA, STO. TOMAS, ISABELA | On-Going | ₱5.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.