Project 25BH0335
DPWH infrastructure contract
Contract ID:
25BH0335
Fingerprint:
18b006e338c424…198a1c4024 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Feb 27, 2026 (8 mos ago)
Description:
BASIC EDUCATIONAL FACILITIES FUND (BEFF) (BATCH 1) - PRIORITY SCHOOL FACILITIES AND NEW CONSTRUCTION OF CLASSROOMS - CONSTRUCTION OF 1STY 3CL VIRGONEZA ES, SAN AGUSTIN, ISABELA
Category:
GAA 2025 DEPED BEFF
Implementing office:
DPWH Isabela 4th DEO · Region II
Contractor:
EXTREME BUILDERS · DPWH contractor code 40315
Location:
Contract amount:
₱8,730,604.00 (₱8.7M)
Funding source:
Outside Infra - GAA 2025 DEPED BEFF
Budget year:
2025
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.