Project 25BJ0028
DPWH infrastructure contract
Contract ID:
25BJ0028
Fingerprint:
ecca1550e2241b…98b673f906 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Feb 14, 2025 (1 yr 8 mo ago)
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BENAY RIVER, BENAY - BARANGAY PALABOT
Category:
GAA 2025 SSP
Implementing office:
DPWH Nueva Vizcaya 2nd DEO · Region II
Contractor:
AMP 723 CONSTRUCTION CORPORATION (FORMERLY: A.M.P. CONSTRUCTION) · DPWH contractor code 16574
Contract amount:
₱142,559,683.78 (₱142.6M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| ca7e522696a9… | Feb 10, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA VIZCAYA 2ND | ₱142,559,683.78 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BJ0049 | Feb 24, 2025 | OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - DUPAX DEL SUR BYPASS, NUEVA VIZCAYA, DUPAX DEL SUR | Completed | ₱94.6M |
| 25BJ0010 | Feb 14, 2025 | OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BAGUMBAYAN FLOOD CONTROL STRUCTURE ALONG BENAY RIVER, BARANGAY BAGUMBAYAN, | On-Going | ₱102.1M |
| 25BJ0024 | Feb 14, 2025 | OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTA FE RIVER, | Completed | ₱140.5M |
| 24BJ0079 | Apr 8, 2024 | BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY STA. MARIA, DUPAX DEL SUR, NUEVA VIZCAYA | Completed | ₱5.4M |
| 24BJ0081 | Apr 8, 2024 | BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING BLISS BARANGAY MANGAYANG, DUPAX DEL SUR, NUEVA VIZCAYA | Completed | ₱4.4M |
| 24BJ0057 | Mar 27, 2024 | BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDING/S FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY ABACA, DUPAX DEL SUR, NUEVA VIZCAYA | Completed | ₱5.4M |
| 24BJ0052 | Mar 4, 2024 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, CAROLOTAN ELEMENTARY SCHOOL, BRGY. CAROLOTAN, DUPAX DEL SUR, NUEVA VIZCAYA | Completed | ₱3.5M |
| 24BJ0006 | Feb 16, 2024 | CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL ALONG BENAY RIVER, PALABOTAN SECTION, DUPAX DEL SUR, NUEVA VIZCAYA | Completed | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.