Project 25CC0090
DPWH infrastructure contract
Contract ID:
25CC0090
Fingerprint:
2a3b023b03432d…3a66afda4f Verified
Status:
On-Going
Physical progress:
95.5%
Timeline:
Start Feb 25, 2025 (1 yr 8 mo ago)
Description:
CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY BAGBAGUIN (PUROK 5), PANDI, BULACAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
TOPNOTCH CATALYST BUILDERS INC. · DPWH contractor code 34061
Contract amount:
₱74,120,218.65 (₱74.1M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2b09249d13a1… | Feb 17, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO | ₱74,120,218.65 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CC0545 | Jun 11, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY BULIHAN, PLARIDEL, BULACAN | On-Going | ₱14.5M |
| 25CC0465 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SIPAT, PLARIDEL, BULACAN | On-Going | ₱14.5M |
| 25CC0532 | May 23, 2025 | CONSTRUCTION OF MULTI- PURPOSE BUILDING BARANGAY SAN JOSE, PLARIDEL, BULACAN | On-Going | ₱14.5M |
| 25C00493 | Apr 14, 2025 | ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MAHARLIKA HIGHWAY, PROVINCE OF BULACAN | On-Going | ₱114.0M |
| 25CC0300 | Apr 8, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PUROK 3, BARANGAY BULIHAN, PLARIDEL, BULACAN | On-Going | ₱92.6M |
| 25CC0301 | Apr 8, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PUROK 1, BARANGAY BAGONG SILANG, PLARIDEL, BULACAN | On-Going | ₱92.8M |
| 25CC0081 | Feb 25, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER AT BARANGAY SANTA LUCIA (PUROK 5 TO PUROK 6), CALUMPIT, BULACAN | On-Going | ₱82.0M |
| 25CC0112 | Feb 25, 2025 | CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE A) AT BARANGAY CULIANIN (PUROK 4), PLARIDEL, BULACAN | On-Going | ₱74.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.