Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25CC0526

DPWH infrastructure contract
Contract ID:
25CC0526
Fingerprint:
1a4a654cd21366…581b394288 Verified
Status:
Not Yet Started
Physical progress:
0%
Timeline:
Start not stated
Description:
CONSTRUCTION MULTI-PURPOSE BUILDING BARANGAY BONGA MENOR, BUSTOS, BULACAN
Category:
Buildings and Facilities
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
WINBUILD ENTERPRISES · DPWH contractor code 48486
Contract amount:
₱18,245,273.24 (₱18.2M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CC0469May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY MALAWAK, BUSTOS, BULACANOn-Going₱18.3M
25CC0470May 23, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE FACILITY (SPORTS COMPLEX), POBLACION, BUSTOS, BULACANOn-Going₱29.0M
25CC0492May 23, 2025CONSTRUCTION OF ROAD AT BARANGAY TALAMPAS , BUSTOS, BULACANOn-Going₱47.6M
25CC0534May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TANAWAN, BUSTOS, BULACANOn-Going₱19.3M
25CD0219Apr 15, 2025IMPROVEMENT OF NORZAGARAY-ANGAT-BUSTOS DIVERSION ROAD IN NORZAGARAY AND ANGAT, BULACANOn-Going₱4.8M
25CC0210Apr 8, 2025CONSTRUCTION OF ROAD AT BARANGAY LICIADA, BUSTOS, BULACANOn-Going₱9.4M
25CC0393Apr 8, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BUSTOS, BULACANOn-Going₱14.5M
25CC0504Apr 4, 2025REHABILITATION OF BRIDGE, PUROK 7, BARANGAY BONGA MAYOR, BUSTOS, BULACANOn-Going₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.