Project 25CD0095
DPWH infrastructure contract
Contract ID:
25CD0095
Fingerprint:
8a8cff6c9bc4f6…582f6a7faa Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 17, 2025 (1 yr 7 mo ago) · Target/actual end Oct 3, 2025
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, MARUNGKO - SAN ROQUE SECTION, STA. 09+605 - STA. 09+905, ANGAT, BULACAN
Category:
GAA 2025 OO-2
Implementing office:
DPWH Bulacan 2nd DEO · Region III
Contractor:
FRANDEL CONSTRUCTION AND DEVELOPMENT CORP. · DPWH contractor code 36116
Contract amount:
₱39,198,642.87 (₱39.2M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| fdaf147b366e… | Mar 5, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 2ND DEO | ₱38,019,663.80 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CD0133 | Jun 26, 2025 | CONSTRUCTION OF BANABAN BRIDGE (PHASE II), BARANGAY BANABAN, ANGAT, BULACAN | On-Going | ₱47.5M |
| 25CD0175 | Apr 15, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, STA. 10+353 - STA. 10+765 (SAN ROQUE SECTION), ANGAT, BULACAN | Completed | ₱49.5M |
| 25CD0182 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS GEN. ALEJO SANTOS HIGHWAY - K0064+000 - K0064+260, K0064+470 - K0064+800, K0065+000 - K0065+140, K0065+355 - K0065+405, K0065+576 - K0065+848, K0065+877 - K0065+1022, K0066 | On-Going | ₱68.0M |
| 25CD0200 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS TERTIARY ROADS GEN. ALEJO SANTOS HIGHWAY - K0060+144 - K0060+531, K0061+181 - K0061+573 | On-Going | ₱28.5M |
| 25CD0225 | Mar 27, 2025 | CONCRETING OF SITIO DAANG MADRE FMR, BRGY. ENCANTO, ANGAT, BULACAN | On-Going | ₱14.5M |
| 25CD0073 | Mar 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY SANTO CRISTO, ANGAT, BULACAN | Completed | ₱9.6M |
| 25CD0094 | Mar 18, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, BARANGAY LAOG TO BARANGAY PINAGTULAYAN, STA. 15+560 STA. 15+648, NORZAGARAY, BULACAN | Completed | ₱39.2M |
| 25CD0100 | Mar 18, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, BARANGAY LAOG TO BARANGAY PINAGTULAYAN, STA. 15+648 STA. 15+714, NORZAGARAY, BULACAN | On-Going | ₱28.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.