Project 25CD0143
DPWH infrastructure contract
Contract ID:
25CD0143
Fingerprint:
0de32a30894be0…ffa4c278ea Verified
Status:
On-Going
Physical progress:
35.1%
Timeline:
Start Apr 2, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG STO. CRISTO RIVER, STA. 10+300 STA.10+450, CITY OF SAN JOSE DEL MONTE, BULACAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Bulacan 2nd DEO · Region III
Contractor:
TRIPLE 8 CONSTRUCTION & SUPPLY, INC. (FORMERLY TRIPLE 8 CONST. & SUPPLY) · DPWH contractor code 10684
Contract amount:
₱93,598,357.89 (₱93.6M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CD0222 | Jul 15, 2025 | REPLACEMENT OF PERMANENT WEAK BRIDGES KAY TIALO BR. (B00136LZ) ALONG NCR/BULACAN BDRY-BIGTE-IPO DAM RD (PHASE III) | Terminated | ₱0 |
| 25OD0367 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 10, PACKAGE 3 LOT 71, BARANGAY 176, CALOOCAN CITY | On-Going | ₱9.7M |
| 25CD0192 | May 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 1, CITY OF SAN JOSE DEL MONTE, BULACAN | On-Going | ₱96.0M |
| 25CD0193 | May 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, (OPERATIONS CENTER - DISTRICT 1), BARANGAY KAYPIAN, CITY OF SAN JOSE DEL MONTE, BULACAN (PHASE III) | On-Going | ₱48.0M |
| 25CD0206 | May 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (ALS BUILDING), TUNGKONG MANGGA ELEMENTARY SCHOOL BARANGAY TUNGKONG MANGGA, CITY OF SAN JOSE DEL MONTE, BULACAN | Completed | ₱19.2M |
| 25CD0154 | Apr 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY MAHARLIKA, SAN JOSE DEL MONTE, BULACAN | Completed | ₱2.9M |
| 25CD0155 | Apr 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY STA. CRUZ 3, SAN JOSE DEL MONTE, BULACAN | Completed | ₱4.8M |
| 25CD0157 | Apr 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY MINUYAN PROPER, SAN JOSE DEL MONTE, BULACAN | Completed | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.