Physical progress:
100%
Timeline:
Start Feb 14, 2025 (1 yr 8 mo ago) · Target/actual end Jul 14, 2025
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LABONG RIVER, BARANGAY SAN JUAN, LICAB, NUEVA ECIJA
Category:
Flood Control and Drainage
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
IJK MAE CONSTRUCTION INC. · DPWH contractor code 35272
Contract amount:
₱48,504,823.35 (₱48.5M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 418a9b6f7241… | Jan 30, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA ECIJA 1ST DE | ₱48,504,823.35 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CE0295 | Jun 2, 2025 | CONSTRUCTION OF ROAD, BARANGAY SAN JOSE, LICAB, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0235 | Apr 2, 2025 | NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LICAB-VICTORIA RD, NUEVA ECIJA | Completed | ₱33.9M |
| 25CE0265 | Apr 2, 2025 | CONSTRUCTION OF ROAD, BARANGAY SANTA MARIA, LICAB, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0105 | Mar 21, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY SANTA LUCIA OLD, ZARAGOZA, NUEVA ECIJA | Completed | ₱48.5M |
| 25CE0019 | Feb 14, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CAINGIN TABING ILOG, GUIMBA, NUEVA ECIJA | Completed | ₱3.0M |
| 25CE0065 | Feb 14, 2025 | REHABILITATION OF ROAD, BARANGAY POBLACION SUR, LICAB, NUEVA ECIJA | Completed | ₱10.7M |
| 24CE0189 | Jul 3, 2024 | NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, TALAVERA - LICAB DIVERSION ROAD, NUEVA ECIJA | Completed | ₱19.4M |
| 24CE0252 | Jul 3, 2024 | CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN LICAB CENTRAL SCHOOL, BARANGAY POBLACION SUR, LICAB, NUEVA ECIJA | Completed | ₱5.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.