Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25CE0188

DPWH infrastructure contract
Contract ID:
25CE0188
Fingerprint:
10ac6eefd3bb71…1b8b757875 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 14, 2025 (1 yr 8 mo ago) · Target/actual end Jul 13, 2025
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ROQUE, LUPAO, NUEVA ECIJA
Category:
Buildings and Facilities
Implementing office:
Contractor:
WIZARD CONCRETE SOLUTIONS AND CONSTRUCTION CORPORATION · DPWH contractor code 21921
As listed: WIZARD CONCRETE SOLUTIONS AND CONSTRUCTION CORPORATION (FORMERLY: WIZARD TRADING & CONSTRUCTION)
Contract amount:
₱4,926,089.56 (₱4.9M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
aaf0d170cec6…Jan 30, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA ECIJA 1ST DE₱4,926,089.56

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CE0208Jun 30, 2025COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING, SAN ANTONIO WESTE ES, BARANGAY SAN ANTONIO WESTE, LUPAO, NUEVA ECIJACompleted₱2.5M
25CE0228Jun 5, 2025CONSTRUCTION OF BARANGAY ROAD IN BARANGAY MANGANDINGAY, SCIENCE CITY OF MUNOZ, NUEVA ECIJACompleted₱9.8M
25CE0212Jun 2, 2025CONSTRUCTION OF SLOPE PROTECTION, BALIWAG BRIDGE ALONG MUÑOZ-LUPAO ROAD, BRGY. AGUPALO WESTE, LUPAO NUEVA ECIJACompleted₱24.5M
25A00201Apr 7, 2025SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 -CLUSTER IV- INSTALLATION/ APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG (1.BAKIT-BAKIT JCT-UMINGAN RD - K0177 + (-170) - K0177 + (-158); 2. BAKIT-BAKIT JCT-UMINGANOn-Going₱3.4M
25CE0137Apr 4, 2025ACCESS ROAD LEADING TO PINSAL FALLS ECOTOURISM PARK, LUPAO, NUEVA ECIJACompleted₱4.9M
25CE0099Mar 20, 2025REHABILITATION OF ROAD, BARANGAY AGUPALO WESTE, LUPAO, NUEVA ECIJACompleted₱9.7M
25CE0225Mar 13, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS, SN JOSE-LUPAO RD - K0171 + 463 - K0172 + 259Completed₱11.3M
25CE0008Feb 21, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALIWAG RIVER, BARANGAY MAPANGPANG, LUPAO, NUEVA ECIJACompleted₱96.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.