Project 25CE0303

DPWH infrastructure contract
Contract ID:
25CE0303
Fingerprint:
d47d06964b68a5…785ada0ea1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 16, 2025 (1 yr 4 mo ago) · Target/actual end Jan 3, 2026
Description:
CONSTRUCTION OF 2 STOREY MULTI-PURPOSE BUILDING, MALIGAYA ELEMENTARY SCHOOL, BARANGAY MALIGAYA, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA
Category:
GAA 2025 SSP
Implementing office:
Contractor:
SYMMETRICON BUILDERS CORP. · DPWH contractor code 37555
Contract amount:
₱16,745,863.33 (₱16.7M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CE0355Dec 3, 2025CONSTRUCTION OF SCHOOL HEALTH FACILITIES, MUNOZ CS, SCIENCE CITY OF MUÑOZ, NUEVA ECIJACompleted₱4.9M
25CE0302Jul 30, 2025CONSTRUCTION OF CLASSROOM BUILDING AT CENTRAL LUZON STATE UNIVERSITY, MUNOZ, NUEVA ECIJACompleted₱19.7M
25CE0203Jul 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LICAONG, SCIENCE CITY OF MUÑOZ, NUEVA ECIJACompleted₱5.9M
25CE0204Jul 1, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, MALIGAYA ES, BARANGAY MALIGAYA, SCIENCE CITY OF MUÑOZ, NUEVA ECIJACompleted₱3.0M
25CE0206Jul 1, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN FELIPE, SCIENCE CITY OF MUÑOZ, NUEVA ECIJACompleted₱4.9M
25CE0213Jul 1, 2025REPLACEMENT OF BOX CULVERT ALONG MUNOZ-TALUGTUG ROAD, BARANGAY CALISITAN, MUÑOZ, NUEVA ECIJACompleted₱11.6M
25CE0205Jun 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ANTONIO, SCIENCE CITY OF MUÑOZ, NUEVA ECIJACompleted₱5.9M
25CE0218Jun 30, 2025CONSTRUCTION OF WATER SYSTEM, BARANGAY VILLA ISLA, SCIENCE CITY OF MUÑOZ, NUEVA ECIJAOn-Going₱4.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.