Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25CG0019

DPWH infrastructure contract
Contract ID:
25CG0019
Fingerprint:
efbbe3302c09db…b18c45ae61 Verified
Status:
On-Going
Physical progress:
74.6%
Timeline:
Start Feb 21, 2025 (1 yr 8 mo ago)
Description:
FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG PAMPANGA RIVER BANK, BARANGAY SULIPAN, APALIT, PAMPANGA
Category:
GAA 2025 OO-2
Implementing office:
DPWH Pampanga 1st DEO · Region III
Contractor:
FERDSTAR BUILDERS INC. · DPWH contractor code 4965
Contract amount:
₱140,407,405.40 (₱140.4M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CG0204Aug 19, 2025CONCRETING OF FARM-TO-MARKET ROAD AT BRGY. SAN JUAN, APALIT, PAMPANGACompleted₱23.6M
25CG0224Aug 19, 2025CONCRETING OF FARM-TO-MARKET-ROAD AT BRGY. CALANTIPE, APALIT, PAMPANGACompleted₱23.7M
25CC0428May 23, 2025REHABILITATION OF ROAD, BARANGAY INAON, PULILAN, BULACANOn-Going₱14.3M
25CG0076Mar 25, 2025SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF APALIT BRIDGE AND BYPASS ROAD AT BARANGAY TABUYUC, APALIT, PAMPANGACompleted₱37.1M
25CG0030Mar 20, 2025FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK (PHASE II), BARANGAY TABUYUC APALIT, PAMPANGAOn-Going₱140.4M
25CG0002Feb 26, 2025FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AT ANGAT-MAASIM RIS, APALIT, PAMPANGACompleted₱13.9M
25CG0058Feb 25, 2025FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF SLOPE PROTECTION STRUCTURE ALONG PAMPANGA RIVER, PULO CAWAYAN, BARANGAY SULIPAN, APALIT, PAMPANGACompleted₱46.8M
25CG0018Feb 21, 2025FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK (PHASE I), BARANGAY TABUYUC, APALIT, PAMPANGAOn-Going₱140.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.