Project 25CJ0046

DPWH infrastructure contract
Contract ID:
25CJ0046
Fingerprint:
d4ae5d069414d4…0e02d4972e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 27, 2025 (1 yr 9 mo ago) · Target/actual end Apr 16, 2025
Description:
RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES GUITEB BR. (B04671LZ) ALONG PANIQUI-RAMOS RD
Category:
Bridges
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
ALPHATEC CHEMICAL CORPORATION · DPWH contractor code 39938
Contract amount:
₱11,760,000.00 (₱11.8M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26CJ0101Jul 13, 2026PREVENTIVE MAINTENANCE PANIQUI-CAMILING-WAWA RD - K0159 + 904 - K0161 + 250On-Going₱59.4M
26CJ0104Jul 13, 2026PREVENTIVE MAINTENANCE RAMOS-PURA RD - K0157 + 145 - K0158 + 206On-Going₱48.4M
25CJ0168May 16, 2025CONSTRUCTION OF TARLAC RIVER RIGHT ROAD DIKE (SEGMENT 1), MONCADA, TARLACOn-Going₱91.7M
25CJ0189May 16, 2025CONSTRUCTION OF TARLAC RIVER RIGHT ROAD DIKE (SEGMENT 2), MONCADA, TARLACOn-Going₱91.7M
25CJ0200May 16, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TARLAC RIVER, LEFT DIKE, BRILLANTE - ADUAS SECTION (ANNEX 9), PANIQUI, TARLACCompleted₱96.5M
25CJ0218May 16, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTA LUCIA RIVER (ANNEX 8), PANIQUI, TARLACOn-Going₱96.5M
25CJ0160Apr 8, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BAKA RIVER, PANIQUI, TARLAC (SEGMENT 29)Completed₱74.3M
25CJ0169Apr 8, 2025PREVENTIVE MAINTENANCE MANILA NORTH RD - K0143 + 670 - K0144 + 995Completed₱96.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.