Project 25CJ0058
DPWH infrastructure contract
Contract ID:
25CJ0058
Fingerprint:
b46e3284e33ad1…ce2415c33b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 27, 2025 (1 yr 9 mo ago) · Target/actual end Apr 26, 2025
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN'S HALL), BARANGAY SAN VICENTE, SAN MANUEL, TARLAC
Category:
Buildings and Facilities
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
ZIONBUILT CONSTRUCTION · DPWH contractor code 55516
Contract amount:
₱4,888,465.00 (₱4.9M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b6d67217d3f2… | Jan 23, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 1ST DEO | ₱4,888,465.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CJ0237 | Jun 20, 2025 | CONSTRUCTION OF SAN MANUEL - VILLASIS BYPASS ROAD (SEGMENT 2), SAN MANUEL, TARLAC | On-Going | ₱96.5M |
| 25CJ0253 | Jun 20, 2025 | CONSTRUCTION OF SAN MANUEL - VILLASIS BYPASS ROAD (SEGMENT 3), SAN MANUEL, TARLAC | On-Going | ₱96.5M |
| 25CJ0274 | Jun 20, 2025 | CONSTRUCTION OF MONCADA - SAN MANUEL BYPASS ROAD (SEGMENT 8), TARLAC | On-Going | ₱96.5M |
| 25CJ0170 | Apr 8, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG PAIT MANOK RIVER, SAN MANUEL, TARLAC (SEGMENT 26) | On-Going | ₱74.3M |
| 25CJ0254 | Apr 8, 2025 | CONSTRUCTION OF SAN MANUEL - VILLASIS BYPASS ROAD (SEGMENT 13), SAN MANUEL, TARLAC | On-Going | ₱96.5M |
| 25CJ0258 | Apr 8, 2025 | CONSTRUCTION OF SAN MANUEL - VILLASIS BYPASS ROAD (SEGMENT 14), SAN MANUEL, TARLAC | On-Going | ₱96.5M |
| 25CJ0268 | Apr 8, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MONCADA-SAN MANUEL BYPASS ROAD, TARLAC (SEGMENT 12) | On-Going | ₱96.5M |
| 24CJ0224 | Mar 15, 2024 | CONSTRUCTION OF MONCADA-SAN MANUEL BYPASS ROAD (SEGMENT C), TARLAC | Completed | ₱48.3M |