Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25CK0126

DPWH infrastructure contract
Contract ID:
25CK0126
Fingerprint:
5e7391bf65d78d…b015e82199 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 13, 2025 (1 yr 4 mo ago) · Target/actual end Jan 24, 2026
Description:
CONSTRUCTION OF SCHOOL BUILDING, MAGAO HIGH SCHOOL, BARANGAY MAGAO, CONCEPCION, TARLAC
Category:
GAA 2025 DEPED BEFF
Implementing office:
DPWH Tarlac 2nd DEO · Region III
Contractor:
HIGH STRENGTH DEV. CORPORATION · DPWH contractor code 31976
Contract amount:
₱19,900,000.00 (₱19.9M)
Funding source:
Outside Infra - GAA 2025 DEPED BEFF
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CK0137Aug 20, 2025EMERGENCY REHABILITATION/RECONSTRUCTION OF EXISTING DIKE ALONG LUCUNG RIVER (MALUPA SECTION) DS OF LUCUNG BRIDGE, LEFT BANK, BRGY. MALUPA, CONCEPCION, TARLAC - PACKAGE CCompleted₱42.9M
25CK0125May 20, 2025CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - RAIN WATER COLLECTORS IN PUBLIC FACILITIES WITHIN 3RD LEGISLATIVE DISTRICT OF TARLAC, CONCEPCION, TARLACCompleted₱2.6M
25CK0075Apr 3, 2025REHABILITATION OF ROAD, LILIBANGAN - CASTILLO ROAD, CONCEPCION, TARLACCompleted₱49.0M
25CK0076Apr 3, 2025REHABILITATION OF ROAD AT BARANGAY LILIBANGAN TO CASTILLO ROAD, CONCEPCION, TARLACCompleted₱96.5M
25CK0083Apr 3, 2025REHABILITATION OF ROAD AT BARANGAY CASTILLO, CONCEPCION, TARLACCompleted₱49.0M
25CK0084Apr 3, 2025REHABILITATION OF ROAD AT BARANGAY SAN VICENTE, CONCEPCION, TARLACOn-Going₱49.0M
25CK0085Apr 3, 2025ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE - TERTIARY ROADS ALONG CONCEPCION - LA PAZ ROAD, K0124+000.00 TO K0126+000.00, CONCEPCION, TARLACCompleted₱96.5M
25CK0086Apr 3, 2025REHABILITATION OF ROAD, BARANGAY STA. CRUZ TO CAFE TO CULATINGAN ROAD, CONCEPCION, TARLACCompleted₱96.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.