Project 25CM0071
DPWH infrastructure contract
Contract ID:
25CM0071
Fingerprint:
d6f619f0ba3957…cff8d7d049 Verified
Status:
On-Going
Physical progress:
45.8%
Timeline:
Start May 21, 2025 (1 yr 5 mo ago)
Description:
CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF SAN MARCELINO MULTI-PURPOSE BUILDING INCLUDING FACILITIES PHASE 2, SAN MARCELINO, ZAMBALES
Category:
GAA 2025 SSP
Implementing office:
DPWH Zambales 2nd DEO · Region III
Contractor:
RAIK CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: RAIK CONSTRUCTION AND SUPPLY) · DPWH contractor code 40660
Contract amount:
₱29,699,739.66 (₱29.7M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CM0061 | May 21, 2025 | CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES AT AGLAO ELEMENTARY SCHOOL, BRGY. AGLAO, SAN MARCELINO, ZAMBALES | Completed | ₱9.8M |
| 25CM0004 | May 19, 2025 | ASSET PRESERVATION PROGRAM, CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS, OLONGAPO-BUGALLON RD., K0153+474-K0153+542, SAN MARCELINO, ZAMBALES | Completed | ₱7.8M |
| 25CM0033 | May 19, 2025 | ASSET PRESERVATION PROGRAM, CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS SAN MARCELINO - SAN ANTONIO - SAN NARCISO RD, K0152+870 - K0153+000, SAN MARCELINO, ZAMBALES | Completed | ₱9.8M |
| 25CM0038 | May 19, 2025 | CSSP - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD LIGHTING, SAN MARCELINO, ZAMBALES | Completed | ₱19.6M |
| 25CM0043 | May 19, 2025 | CSSP, BIP, ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT SAN MARCELINO, ZAMBALES | On-Going | ₱29.0M |
| 25CM0060 | May 19, 2025 | CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. CONSUELO SUR, SAN MARCELINO, ZAMBALES | Completed | ₱6.9M |
| 25CM0062 | May 19, 2025 | CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. RABANES, SAN MARCELINO, ZAMBALES | Completed | ₱9.9M |
| 25CM0063 | May 19, 2025 | CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. SAN GUILLERMO, SAN MARCELINO, ZAMBALES | Completed | ₱6.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.