Project 25CN0101
DPWH infrastructure contract
Contract ID:
25CN0101
Fingerprint:
b3e77e830ffaa1…dc14c83e15 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 10, 2025 (1 yr 5 mo ago) · Target/actual end May 18, 2026
Description:
CONSTRUCTION OF DRAINAGE CANAL, POBLACION 4, SAN LUIS, AURORA
Category:
GAA 2025 SSP
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
VANMARVIL CONSTRUCTION · DPWH contractor code 19224
Contract amount:
₱14,475,000.00 (₱14.5M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0199 | Dec 12, 2025 | REPAIR/REHABILITATION OF 2 CLASSROOMS, KALAPNIT ES, SAN LUIS, AURORA | On-Going | ₱2.2M |
| 25CN0208 | Nov 25, 2025 | CONSTRUCTION OF 1 STOREY 2 CLASSROOM SCHOOL BUILDING, KALAPNIT ES, SAN LUIS, AURORA | On-Going | ₱4.9M |
| 25CN0167 | Jul 18, 2025 | CONSTRUCTION (COMPLETION) OF DRAINAGE CANAL, BARANGAY SAN ISIDRO, SAN LUIS, AURORA | On-Going | ₱3.8M |
| 25CN0019 | Jul 14, 2025 | REPLACEMENT OF PERMANENT WEAK BRIDGES, DIPAWAN BR. (B02825LZ) ALONG NUEVA ECIJA - AURORA RD | On-Going | ₱19.2M |
| 25CN0159 | Jul 7, 2025 | CONSTRUCTION OF BALER - SAN LUIS - DINGALAN ROAD, BALER, AURORA | Completed | ₱96.5M |
| 25CN0014 | Jul 4, 2025 | ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, NUEVA ECIJA - AURORA RD, K0185 + 650 - K0185 + 670, K0199 + 150 - K0199 + 180, K0208 + 300 - K0209 + 330 | Completed | ₱12.9M |
| 25CN0165 | Jun 16, 2025 | REHABILITATION OF MULTI - PURPOSE BUILDING, SAN LUIS CENTRAL ELEMENTARY SCHOOL, SAN LUIS, AURORA | On-Going | ₱4.8M |
| 25CN0065 | Jun 9, 2025 | CONSTRUCTION OF WATER SYSTEM, BARANGAY NONONG SR., SAN LUIS, AURORA | Completed | ₱9.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.