Project 25CN0166
DPWH infrastructure contract
Contract ID:
25CN0166
Fingerprint:
a0f22fa196ea99…f53c9e169f Verified
Status:
Terminated
Physical progress:
0%
Timeline:
Start Aug 27, 2025 (1 yr 2 mo ago) · Target/actual end Oct 10, 2025
Description:
CONSTRUCTION OF ROAD (PHASE 2), BARANGAY ZABALI, BALER, AURORA
Category:
GAA 2025 SSP
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
R.N.G.M. CONSTRUCTION CORPORATION (FORMERLY: R.N.G.M. CONSTRUCTION) · DPWH contractor code 20281
Contract amount:
₱0.00 (₱0)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0157 | Sep 1, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING , BARANGAY ZABALI, BALER, AURORA | On-Going | ₱99.0M |
| 25CN0096 | Aug 4, 2025 | CONSTRUCTION OF ROAD, BARANGAY ZABALI, BALER, AURORA | Completed | ₱28.9M |
| 25CN0168 | Jul 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY CALABUANAN, BALER, AURORA | On-Going | ₱4.8M |
| 25CN0116 | Jul 7, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY RESERVA, BALER, AURORA | On-Going | ₱6.9M |
| 25CN0182 | Jul 3, 2025 | RAINWATER COLLECTOR SYSTEM | On-Going | ₱2.6M |
| 25CN0150 | Jun 10, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SABANG, BALER, AURORA | On-Going | ₱4.9M |
| 25CN0021 | May 28, 2025 | REPLACEMENT OF PERMANENT WEAK BRIDGES, PUDOC BR. (B03014LZ) ALONG BALER - CASIGURAN RD (BALER - DINADIAWAN) | On-Going | ₱65.7M |
| 25CN0132 | May 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 5, BALER, AURORA | On-Going | ₱5.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.