Project 25DH0039
DPWH infrastructure contract
Contract ID:
25DH0039
Fingerprint:
95c0586a816719…8db215a617 Verified
Status:
On-Going
Physical progress:
0%
Timeline:
Start Aug 21, 2025 (1 yr 2 mo ago)
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PANGIL LAKESHORE, PANGIL, LAGUNA
Category:
Flood Control and Drainage
Implementing office:
DPWH Laguna 1st DEO · Region IV-A
Contractor:
11-16 CONSTRUCTION · DPWH contractor code 29646
Contract amount:
₱93,595,174.24 (₱93.6M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24DH0079 | Sep 5, 2024 | CONSTRUCTION OF ROAD WITH BOX CULVERT, SITIO SAUDI, BARANGAY BALIAN, PANGIL, LAGUNA | On-Going | ₱8.2M |
| 24DH0072 | Aug 23, 2024 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES BALIAN BR. (B03194LZ) ALONG PAETE-FAMY POB. RD., PANGIL, LAGUNA | Completed | ₱1.4M |
| 24DH0037 | Mar 22, 2024 | CONSTRUCTION (COMPLETION) OF MULTIPURPOSE BUILDING (COVERED COURT) AT BARANGAY ISLA, PANGIL, LAGUNA | Completed | ₱3.0M |
| 24DH0030 | Mar 1, 2024 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PANGIL RIVER, PANGIL, LAGUNA | Completed | ₱96.5M |
| 24DH0020 | Feb 23, 2024 | CONSTRUCTION OF RIVER CONTROL ALONG PANGIL RIVER, PANGIL, LAGUNA | Completed | ₱77.9M |
| 23DH0074 | Jul 12, 2023 | CONSTRUCTION OF ROAD, BARANGAY NATIVIDAD, PANGIL, LAGUNA | Completed | ₱23.2M |
| 23DH0048 | Apr 1, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY SAN JOSE, PANGIL, LAGUNA | Completed | ₱4.8M |
| 23DH0010 | Feb 9, 2023 | CONSTRUCTION OF RIVER CONTROL ALONG PANGIL RIVER, PANGIL, LAGUNA | Completed | ₱72.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.