Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25DM0050

DPWH infrastructure contract
Contract ID:
25DM0050
Fingerprint:
9e48bc0b7e6414…bb1dbd90eb Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 26, 2025 (1 yr 7 mo ago) · Target/actual end Mar 2, 2026
Description:
ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - SN FRANCISCO - SN ANDRES - SN NARCISO RD - K0325+465 - K0325+888, K0325+930 - K0325+977, K0332+147 - K0332+181, SAN FRANCISCO
Category:
GAA 2025 OO-1
Implementing office:
DPWH Quezon 3rd DEO · Region IV-A
Contract amount:
₱79,897,471.04 (₱79.9M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DM0180Jan 14, 2026CONSTRUCTION OF CLASSROOMS, BUTANGUIAD ELEMENTARY SCHOOL, SAN FRANCISCO, QUEZONCompleted₱5.0M
25DM0185Jan 12, 2026CONSTRUCTION OF CLASSROOMS, MABUNGA NHS, SAN FRANCISCO, QUEZONOn-Going₱15.0M
25DM0170Nov 13, 2025CONSTRUCTION OF QUEZON PROVINCIAL HOSPITAL NETWORK - SAN FRANCISCO (PHASE 3), QUEZONOn-Going₱93.5M
25DM0162Aug 18, 2025CONSTRUCTION OF SCHOOL BUILDING, MARCIAL B. VILLANUEVA NATIONAL HIGH SCHOOL, BARANGAY CAWAYAN 1, SAN FRANCISCO, QUEZONCompleted₱5.0M
25DM0164Aug 18, 2025CONSTRUCTION OF SCHOOL BUILDING, YUGNO ELEMENTARY SCHOOL, SITIO YUGNO, BARANGAY CAMFLORA, SAN ANDRES, QUEZONCompleted₱5.0M
25DM0091Jul 11, 2025CONSTRUCTION OF SMALL RIVER IMPROVEMENT PROJECT, CASAY SIS, SAN FRANCISCO, QUEZONOn-Going₱14.7M
25DM0079Jun 25, 2025CONSTRUCTION OF ROAD, BARANGAY ILAYANG TAYUMAN, SAN FRANCISCO, QUEZONOn-Going₱19.6M
25DM0115Jun 3, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0345 + 000 - K0347 + 000Completed₱93.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.