Project 25DN0063

DPWH infrastructure contract
Contract ID:
25DN0063
Fingerprint:
19b088b49b9aa8…ec8db73214 Verified
Status:
On-Going
Physical progress:
44.5%
Timeline:
Start Mar 27, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF MULTI-PURPOSE FACILITY, RIZAL POLICE PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT)
Category:
GAA 2025 SSP
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
FRANZCOR TRADING & CONSTRUCTION · DPWH contractor code 18082
Contract amount:
₱9,701,448.97 (₱9.7M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
641504bd5bd3…Mar 14, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED₱9,701,448.97

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25O00107Jun 5, 2025REHABILITATION AND IMPROVEMENT OF RETARDING POND AT TAPAYAN PUMPING STATION AND TRIBUTARIES, PASIG CITYOn-Going₱189.1M
25OB0268May 20, 2025REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 5)On-Going₱14.0M
25OB0269May 20, 2025REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 6)On-Going₱14.0M
25OB0270May 20, 2025REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 7)On-Going₱14.0M
25DN0069Apr 8, 2025CONSTRUCTION OF ROAD AT ROAD 11, 12, 13, 14, 15, 16 AND 17, PUROK 3, LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT)On-Going₱19.6M
25DN0080Mar 27, 2025CONSTRUCTION OF ROAD AT BLK. 16 AND 17, PUROK 2 LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT)On-Going₱15.2M
25DN0048Mar 26, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAYTAY RIVER, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT)On-Going₱49.0M
25DN0050Mar 26, 2025CONSTRUCTION OF ROAD AT HIGHWAY 2000, PHASE 2, TAYTAY, RIZAL (FIRST DISTRICT)Completed₱49.0M