FY2026 GAA: ₱6.79T
PisoScan

Project 25DN0106

DPWH infrastructure contract
Contract ID:
25DN0106
Fingerprint:
800949841cb8c1…970fff9bc2 Verified
Status:
On-Going
Physical progress:
80%
Timeline:
Start May 29, 2025 (1 yr 5 mo ago)
Description:
CONSTRUCTION OF BOX CULVERT CONNECTING BARANGAY JANOSA AND BARANGAY KAYTOME BINANGONAN, RIZAL (FIRST DISTRICT)
Category:
GAA 2025 SSP
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
OLIVER AQUINO CONSTRUCTION · DPWH contractor code 36827
Contract amount:
₱4,900,000.00 (₱4.9M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DN0097Jun 26, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MANILA EAST RD - K0033+276 - K0033+551, RIZAL (FIRST DISTRICT)On-Going₱7.1M
25DN0098May 29, 2025CONSTRUCTION OF ROAD AT BARANGAY ITHAN TO BARANGAY KALINAWAN, BINANGONAN, RIZAL (FIRST DISTRICT)On-Going₱19.0M
25DN0101May 29, 2025CONSTRUCTION OF FLOOD STRUCTURE, CREEK, W. CERRERO GOING TO F. CEQUEÑA, BARANGAY MACAMOT, BINANGONAN, RIZAL (FIRST DISTRICT)Completed₱9.5M
25DN0112May 29, 2025FY 2025 CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM BINANGONAN, RIZAL (FIRST DISTRICT)On-Going₱2.6M
25DN0067May 27, 2025CONSTRUCTION OF ROAD AT CABLE WAY GOING TO KASINAY, BARANGAY MACAMOT AND BARANGAY DARANGAN, BINANGONAN, RIZAL (FIRST DISTRICT)Completed₱67.5M
25DN0044May 26, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN JUAN CREEK, BINANGONAN, RIZAL (FIRST DISTRICT)Completed₱19.6M
25DN0056May 26, 2025CONSTRUCTION OF BREAKWATER, BARANGAY KALINAWAN GOING TO BARANGAY PIPINDAN, BINANGONAN, RIZAL (FIRST DISTRICT)On-Going₱9.5M
25DN0016May 23, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MANILA EAST RD - K0028+777 - K0029+100, RIZAL (FIRST DISTRICT)Completed₱10.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.