Project 25DQ0015

DPWH infrastructure contract
Contract ID:
25DQ0015
Fingerprint:
810d9eda4dedaf…380aff076c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 16, 2025 (1 yr 6 mo ago) · Target/actual end Feb 6, 2026
Description:
CONSTRUCTION OF REVETMENT ALONG CARMONA RIVER, PHASE 2, BARANGAY CABILANG BAYBAY, CARMONA CITY, CAVITE
Category:
GAA 2025 OO-2
Implementing office:
DPWH Cavite 3rd DEO · Region IV-A
Contractor:
OMNICON BUILDERS · DPWH contractor code 22816
Contract amount:
₱83,031,472.76 (₱83.0M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
2da867d02baa…Mar 24, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAVITE 3RD DISTRIC₱83,031,472.76

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26DQ0016Jun 16, 2026PREVENTIVE MAINTENANCE - PRIMARY ROADS - MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K0017 + 027 - K0017 + 479On-Going₱21.0M
25DQ0004Apr 16, 2025CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT ALONG CARMONA-BIÑAN RIVER, PHASE 1, BARANGAY LANTIC, CARMONA CITY, CAVITEOn-Going₱81.7M
25DQ0011Apr 16, 2025CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT ALONG CARMONA-BIÑAN RIVER, PHASE 2, BARANGAY LANTIC, CARMONA CITY, CAVITEOn-Going₱81.4M
25DQ0072Apr 16, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POB 3, GENERAL MARIANO ALVAREZ, CAVITECompleted₱4.9M
25DQ0081Apr 16, 2025CONSTRUCTION OF REVETMENT ALONG CARMONA RIVER, BARANGAY MABUHAY TO BARANGAY LANTIC, PHASE 1, CARMONA CITY, CAVITEOn-Going₱93.7M
25DQ0088Apr 16, 2025CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG CARMONA RIVER, PHASE 1, GEN. MARIANO ALVAREZ, CAVITEOn-Going₱94.8M
25DQ0103Apr 16, 2025CONSTRUCTION OF DPWH QUALITY ASSURANCE LABORATORY BUILDING, DPWH CAVITE 3RD DISTRICT ENGINEERING OFFICE, CARMONA CITY, CAVITEOn-Going₱19.4M
25DQ0069Apr 15, 2025ROAD WIDENING - PRIMARY ROADS - JUANITO R. REMULLA, SR. RD - K0042 + 633 - K0042 + 655, K0044 + 015 - K0044 + 195, K0044 + 788 - K0044 + 821, K0044 + 966 - K0045 + 170, K0045 + 458 - K0045 + 600On-Going₱26.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.