Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25DQ0108

DPWH infrastructure contract
Contract ID:
25DQ0108
Fingerprint:
5b0b0a987cc5d2…b00f414d1a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 5, 2025 (1 yr 5 mo ago) · Target/actual end Jan 15, 2026
Description:
CONCRETING OF BRGY. IBA FMR, BRGY. IBA, SILANG, CAVITE
Category:
GAA 2025 DA FMR
Implementing office:
DPWH Cavite 3rd DEO · Region IV-A
Contractor:
CMMJ CONSTRUCTION · DPWH contractor code 51415
Contract amount:
₱14,477,208.41 (₱14.5M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DQ0114Aug 13, 2025REHABILITATION OF ROAD, BARANGAY KALUBKOB, SILANG, CAVITECompleted₱9.6M
25DQ0109Jul 2, 2025CAPITAL OUTLAY - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM - VICENTE P. VILLANUEVA MEMORIAL SCHOOL, DASMARIÑAS CITY, CAVITE; MALINTA ELEMENTARY SCHOOL, BRGY. SAMPALOC II, DASMARIÑAS CITY, CAVITE; CAVITE STATE UNIVERSITY, BRGY.On-Going₱2.6M
25DQ0083Jun 26, 2025CONSTRUCTION OF ROAD WITH DRAINAGE, BARANGAY LANGKAAN 2, DASMARINAS CITY, CAVITEOn-Going₱48.0M
25DQ0089Jun 26, 2025CONSTRUCTION OF BANK AND SLOPE STRUCTURES AND OTHER IMPROVEMENTS ALONG CARMONA RIVER, FROM BRGY BULIHAN TO BRGY IPIL, SILANG, CAVITEOn-Going₱97.2M
25DQ0095Jun 26, 2025CONSTRUCTION OF ROAD NETWORK FROM HOSTEL TO ACADEMICS BUILDING, PNPA, CAMP GENERAL MARIANO N. CASTAÑEDA, SILANG, CAVITEOn-Going₱20.8M
25DQ0107Jun 5, 2025OPENING AND CONCRETING OF BRGY. MALABAG FMR, BRGY. MALABAG, SILANG, CAVITECompleted₱5.8M
25DQ0026Apr 16, 2025REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY MAGUYAM, SILANG, CAVITECompleted₱4.9M
25DQ0071Apr 16, 2025CONSTRUCTION (COMPLETION) OF BRIDGE CONNECTING BARANGAY LUMIL AND BARANGAY CABANGAAN, SILANG, CAVITEOn-Going₱84.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.