Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25E00107

DPWH infrastructure contract
Contract ID:
25E00107
Fingerprint:
98e34fdbe170bf…20ebd6391a Verified
Status:
On-Going
Physical progress:
64.7%
Timeline:
Start Mar 27, 2025 (1 yr 7 mo ago)
Description:
FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF SLOPE PROTECTION STRUCTURE (KIWIT BR. 1), BUSUANGA, PALAWAN
Category:
GAA 2025 OO-2
Implementing office:
DPWH MIMAROPA Region · MIMAROPA Region
Contract amount:
₱72,493,845.91 (₱72.5M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25E00099Jun 19, 2025ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- TERTIARY ROADS, CORON-BUSUANGA ROAD, K0055+000-K0055+918, BUSUANGA, PALAWANOn-Going₱53.3M
25E00104Mar 27, 2025ASSET PRESERVATION PROGRAM- REHAB./RECONST. OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE- SECONDARY ROADS, CORON-BUSUANGA ROAD, K0057+700-K0057+823, BUSUANGA, PALAWANOn-Going₱186.1M
25EE0005Mar 18, 2025CONSTRUCTION/IMPROVEMENT OF ROAD JUNCTION OF SITIO OCAM-OCAM ROAD TO BUSUANGA, BUSUANGA, PALAWANCompleted₱4.9M
25E00240Mar 12, 2025FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF SLOPE PROTECTION STRUCTURE ALONG BANABA BRIDGE, STA. 000+237.40-STA. 000+400, BUSUANGA, PALAWANOn-Going₱92.4M
25EE0001Mar 1, 2025RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - BANABA BRIDGE (B00025CR) ALONG CORON - BUSUANGA ROAD, BUSUANGA, PALAWANCompleted₱9.8M
25EE0002Mar 1, 2025RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - BOGTONG BRIDGE (B00044CR) ALONG CORON-BUSUANGA ROAD, BUSUANGA, PALAWANOn-Going₱9.8M
25EE0003Mar 1, 2025RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - BULUANG BRIDGE 1 (B00047CR) ALONG CORON-BUSUANGA ROAD, BUSUANGA, PALAWANCompleted₱9.8M
24EE0130May 26, 2024PACKAGE V-CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM PROJECTS: 1. CONSTRUCTION OF WATER SUPPLY SYSTEM PROJECT (LEVEL II), PHASE II, CASIAN, TAYTAY 2. CONSTRUCTION OF WATER SUPPLY SYSTEM PROJECT (LEVEL II), PHASE II, LIMINANGCONG, TAYTAY 3. CONSTROn-Going₱32.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.