On-Going
Physical progress:
83.4%
Timeline:
Start Feb 15, 2025 (1 yr 8 mo ago)
Description:
COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD, PHASE 3, BRGY. TUGDAN, TABLAS, ROMBLON
Category:
GAA 2025 SSP
Implementing office:
DPWH MIMAROPA Region · MIMAROPA Region
Contract amount:
₱230,152,204.38 (₱230.2M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
620f50e16d1b…Feb 10, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION IV-B₱230,152,204.38

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25EH0154May 27, 2025CONSTRUCTION OF ROAD, BARANGAY LAWAN TO BARANGAY SAN ISIDRO (PHASE 2), ALCANTARA, ROMBLONOn-Going₱93.5M
25EH0161May 27, 2025CONSTRUCTION OF ROAD, SITIO MAGSUPOT TO SITIO ILAYA, BARANGAY CALAGONSAO, ALCANTARA, ROMBLONOn-Going₱140.2M
25EH0116May 23, 2025CONSTRUCTION OF CAMILI- RNIT ACCESS ROAD, ALCANTARA, ROMBLONOn-Going₱11.6M
25EH0088May 21, 2025CONSTRUCTION OF ROAD, ALCANTARA TO ODIONGAN, ALCANTARA, ROMBLONOn-Going₱142.7M
25EH0003Mar 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), ALCANTARA NATIONAL HIGH SCHOOL, ALCANTARA, ROMBLONCompleted₱4.9M
25EH0006Mar 24, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), ROMBLON NATIONAL INSTITUTE OF TECHNOLOGY - RNIT, PHASE I, BARANGAY POBLACION, ALCANTARA, ROMBLONCompleted₱5.9M
25EH0037Mar 24, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), ALCANTARA NATIONAL HIGH SCHOOL, SENIOR HIGH SCHOOL, ALCANTARA, ROMBLONCompleted₱4.9M
25E00141Mar 12, 2025ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC P[UBLIC BUILDINGS/FACILITIES- CONST. OF COASTAL ROAD, BRGY. CALAGONSAO, ALCANTARA, ROMBLONOn-Going₱276.2M