Project 25EA0100

DPWH infrastructure contract
Contract ID:
25EA0100
Fingerprint:
8a58bf863e5d8e…b076642db6 Verified
Status:
On-Going
Physical progress:
79.4%
Timeline:
Start Feb 2, 2026 (9 mos ago)
Description:
REPAIR/REHABILITATION OF CLASSROOMS, BOGNUYAN ES, GASAN, MARINDUQUE
Category:
GAA 2025 DEPED BEFF
Implementing office:
DPWH Marinduque DEO · MIMAROPA Region
Contractor:
Contract amount:
₱7,968,946.25 (₱8.0M)
Funding source:
Outside Infra - GAA 2025 DEPED BEFF
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25EA0102Mar 10, 2026LAST MILE SCHOOLS PROGRAM - BACONGBACONG ES, GASAN, MARINDUQUEOn-Going₱10.8M
25EA0018Mar 21, 2025NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0095+526 - K0097+077, K0097+137 - K0097+812Completed₱103.0M
25EA0033Mar 21, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (PHASE 2), BARANGAY LIBTANGIN, GASAN, MARINDUQUECompleted₱2.9M
25EA0002Feb 21, 2025FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION OF MASIGA FLOOD CONTROL STRUCTURE, BARANGAY MASIGA, GASAN, MARINDUQUECompleted₱38.8M
24EA0096Jan 28, 2025SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF TIGUION RIVER CONTROL, GASAN, MARINDUQUECompleted₱48.2M
24EA0063Mar 18, 2024CONCRETING OF BRGY. BOGNUYAN FMR PHASE II, BRGY. BOGNUYAN, GASAN,MARINDUQUECompleted₱14.9M
24EA0072Mar 15, 2024CONSTRUCTION OF BAHI-TAPUYAN ROAD, GASAN, MARINDUQUECompleted₱96.5M
24E00003Mar 2, 2024FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF GASAN SHORE PROTECTION/BOULEVARD, GASAN, MARINDUQUEOn-Going₱241.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.