Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25EH0025

DPWH infrastructure contract
Contract ID:
25EH0025
Fingerprint:
e35bf9ff66c41c…9c21f48f3b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2025 (1 yr 7 mo ago) · Target/actual end Jul 24, 2025
Description:
REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG TABLAS CIRCUMFERENTIAL ROAD, K0114+786.50 - K0114+912.70, TABLAS ISLAND, ROMBLON
Category:
GAA 2025 OO-1
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
TWIN DRAGON CONSTRUCTION · DPWH contractor code 11392
Contract amount:
₱6,500,367.52 (₱6.5M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1560ba1c8402…Mar 11, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO₱6,500,367.52

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25EH0148Jun 25, 2025CONSTRUCTION OF SCHOOL BUILDING, AGNOCNOC ELEMENTARY SCHOOL, FERROL, ROMBLONOn-Going₱4.9M
25EH0152May 27, 2025CONSTRUCTION OF ROAD, CLARO M. RECTO TO SITIO SAN ISIDRO, BARANGAY MALILICO, ODIONGAN, ROMBLONOn-Going₱74.8M
25EH0018Mar 28, 2025CONSTRUCTION OF ROAD, SITIO ATABAY, TUBIGON, FERROL, ROMBLONCompleted₱19.3M
25EH0049Mar 28, 2025REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG TABLAS CIRCUMFERENTIAL ROAD, K0121+724.00 - K0122+121 (AS PER RBIA), K0121+724.00 - K0122+112 (AS PER ACTUAL), TABLAS ISLAND, ROMBLONOn-Going₱28.4M
25E00150Feb 15, 2025BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRTUCTURE, TINGARAYOn-Going₱247.5M
25E00151Feb 15, 2025BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRUCTURE, TINGARAY RIVER, UPSTREAM R/S, BRGY. POBLACION, FERROL, ROMBLONOn-Going₱247.5M
24EH0057Jul 10, 2024REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG TABLAS CIRCUMFERENTIAL RD, K0120+562.16 - K0121+724 (AS PER RBIA), K0120+583.16 - K0121+724 (AS PER ACTUAL), TABLAS ISLAND, ROMBLONCompleted₱71.5M
24EH0133Apr 22, 2024CONSTRUCTION OF SITIO LUPOG TO SITIO BARIRI ROAD, FERROL, ROMBLON PHASE 2, FERROL, ROMBLONCompleted₱48.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.