Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25EH0040

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","25EH0040","CONSTRUCTION OF CAMPALINGO FLOOD CONTROL STRUCTURE ALONG SIBUYAN CIRCUMFERENTIAL ROAD, PHASE 2, BRGY. CAMPALINGO, SAN FERNANDO, ROMBLON","GAA 2025 OO-2","On-Going",27125694.89,0,100,"Romblon DEO","MIMAROPA Region","MT. GUITING-GUITING CONSTRUCTION (17412)","2025-04-11",null,2025,"Regular Infra - GAA 2025 OO-2",12.29181,122.61774,"1705913000","1705900000"]
SHA-256
879c18d837c50465daabb78963cf1591c45cea25021bb42e6c0d12665ac3c6a8

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.