Project 25EI0039
DPWH infrastructure contract
Contract ID:
25EI0039
Fingerprint:
64560909068f7a…78912b0cd1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 11, 2025 (1 yr 8 mo ago) · Target/actual end Jun 8, 2025
Description:
REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROAD - CALAPAN SOUTH ROAD - K0166+006.00 - K0166+261.00, K0168+605.00 - K0168+1000.00, MANSALAY-BULALACAO, ORIENTAL MINDORO
Category:
GAA 2025 SSP
Implementing office:
DPWH Southern Mindoro DEO · MIMAROPA Region
Contractor:
LUCKY SHINING STAR DEVELOPMENT CORP. · DPWH contractor code 53982
Contract amount:
₱13,100,051.81 (₱13.1M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 7da6da27592d… | Feb 28, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTHERN MINDORO D | ₱13,100,051.81 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26EI0128 | Jul 7, 2026 | ROAD WIDENING - SECONDARY ROADS CALAPAN SOUTH RD - K0142+ 019 - K0142 + 134, K0142 + 371 - K0142 + 726, K0143 + 577 - K0143 + 714, K0143 + 847 - K0144 + 011, K0146 + 535 - K0146 + 751, K0151 + 104 - K0151 + 167, MANSALAY, ORIENTAL MINDORO | On-Going | ₱43.0M |
| 25EI0065 | Mar 25, 2025 | PREVENTIVE MAINTENANCE - SECONDARY ROADS - ALONG CALAPAN SOUTH RD. K0153+000 - K0153+493, MANSALAY, ORIENTAL MINDORO | Completed | ₱34.2M |
| 25EI0066 | Mar 25, 2025 | CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF WASIG RIVER CONTROL STRUCTURE, BARANGAY WASIG, MANSALAY, ORIENTAL MINDORO | Completed | ₱29.0M |
| 25EI0076 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (SK BUILDING) AT BARANGAY POBLACION, MANSALAY, ORIENTAL MINDORO | Completed | ₱4.9M |
| 25EI0104 | Mar 25, 2025 | CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY BONBON, MANSALAY, ORIENTAL MINDORO, PHASE II | Completed | ₱2.9M |
| 25EI0109 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BALUGO NATIONAL HIGH SCHOOL, BARANGAY BALUGO, MANSALAY, ORIENTAL MINDORO, PHASE II | Completed | ₱4.9M |
| 25EI0134 | Mar 25, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY B. DEL MUNDO, MANSALAY, ORIENTAL MINDORO, PHASE II | Completed | ₱2.9M |
| 25EI0003 | Mar 13, 2025 | CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - CALAPAN SOUTH RD - K0153+480 - K0153+861, MANSALAY, ORIENTAL MINDORO | Completed | ₱13.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.