Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25F00364

DPWH infrastructure contract
Contract ID:
25F00364
Fingerprint:
cec51b99f4cd70…c9080b4490 Verified
Status:
On-Going
Physical progress:
39.6%
Timeline:
Start Jun 20, 2025 (1 yr 4 mo ago)
Description:
ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-REHABILITATION OF REVETMENT, BARANGAY TARUSANAN, CAMALIGAN, CAMARINES SUR, CA
Category:
GAA 2025 OO-2
Implementing office:
DPWH Region V · Region V
Contractor:
PHILWORKS CONSTRUCTION AND SUPPLY · DPWH contractor code 32103
As listed: PHILWORKS CONSTRUCTION & SUPPLY
Contract amount:
₱121,555,645.95 (₱121.6M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
24FF0088Aug 28, 2024CLUSTER 2-CONST. OF RAIN WATER COLLECTOR SYSTEM(RWCS) OCAMPO,CALABANGA & CAMALIGAN CAMARINES SURCompleted₱2.9M
24F00195Apr 8, 2024ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BICOL RIVER FLOOD MITIGATION STRCompleted₱148.6M
24F00205Apr 8, 2024ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-REHABILITATION OF BICOL RIVER FLOOD CONTROL (DUGCompleted₱135.1M
24FF0008Feb 23, 2024BIP;ACCESS ROADS & OR BRIDGES FROM THE NATL. ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONST. OF ROAD BRGY. SUA CAMALIGAN CAMARINES SURCompleted₱4.8M
23FF0100Jan 9, 2024CONST. OF 4 STY 16 CL,CAMALIGAN NATIONAL HIGH SCHOOL (FORMER STO TOMAS NATIONAL HIGH SCHOOL) UNDER CY 2023 BFF BATCH 1 NEW CONSTRUCTION CAMALIGAN CAMARINES SURCompleted₱66.4M
23FF0077Sep 4, 2023CONSTRUCTION OF MULTI PURPOSE BUILDING,BRGY. SAN MATEO CAMALIGAN CAMARINES SURCompleted₱4.9M
23FF0036Apr 11, 2023002;FLOOD MANAGEMENT PROG.-CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS-REHAB.OF BICOL RIVER FLOOD CONTROL(SAN MATEO-SITIO GOGON SECTION)CAMALIGAN CAM. SURCompleted₱66.8M
23FE0069Apr 5, 2023OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL ALONG BICOL RIVER, BRGY. DISTRICT II, GAINZA, CAMARINES SURCompleted₱72.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.