Project 25FA0022
DPWH infrastructure contract
Contract ID:
25FA0022
Fingerprint:
da8d5546fe816c…cf2a96291a Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Mar 21, 2025 (1 yr 7 mo ago)
Description:
REHB./RECONST./UPGRADING OF DAMAGED PAVED RDS.-SECONDARY RDS.: DAANG MAHARLIKA JCT.-LEG.-STO. DOMINGO-TABACO-CAM. SUR BDRY. RD.-K0574+700-K0575+096
Category:
Roads
Implementing office:
DPWH Albay 1st DEO · Region V
Contractor:
OMEGA CONTRACTING AND DEVELOPMENT CORP. · DPWH contractor code 41283
Contract amount:
₱15,886,780.00 (₱15.9M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FA0042 | Nov 3, 2025 | CONSTRUCTION OF BELEN WATER SYSTEM AT BELEN, TIWI, ALBAY | On-Going | ₱5.0M |
| 24FA0058 | Sep 24, 2024 | CLUSTER 15-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II AT BACACAY, MALILIPOT, MALINAO & TIWI, ALBAY | Completed | ₱49.5M |
| 24FA0052 | Sep 17, 2024 | CLUSTER 11 - CONSTRUCTION/IMPROVEMENT OF VARIOUS ACCESSS ROADS IN THE FIRST DISTRICT OF ALBAY | Completed | ₱58.8M |
| 24FA0032 | Jul 19, 2024 | CONCRETING OF PUROK 5, BRGY. JOROAN FMR, BRGY. JOROAN, TIWI, ALBAY | On-Going | ₱15.9M |
| 24FA0036 | Jun 21, 2024 | CLUSTER 4-REHAB./RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG MT. MAYON PARK ROAD BUANG TABACO CITY, ALBAY AND ALONG DM JCT. LEGAZPI-STO. DOMINGO-TABACO-CAM SUR BDRY. ROAD, TIWI, ALBAY | Completed | ₱58.1M |
| 24FA0018 | Apr 19, 2024 | CONSTRUCTION OF FLOOD CONTROL ( ROAD DIKE) PROTECTING MAYNONONG ELEMENTARY SCHOOL, TIWI, ALBAY | Completed | ₱62.7M |
| 24FA0005 | Feb 15, 2024 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS: TIWI BY-PASS ROAD (ALTERNATE ROUTE), ALBAY | Completed | ₱49.0M |
| 24FA0010 | Feb 13, 2024 | CONSTRUCTION OF JOROAN RIVER CONTROL (DOWNSTREAM), TIWI, ALBAY | Completed | ₱39.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.