Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25FF0011

DPWH infrastructure contract
Contract ID:
25FF0011
Fingerprint:
9b72b9ccabcc0a…89ee90dcd3 Verified
Status:
On-Going
Physical progress:
50.9%
Timeline:
Start Jun 5, 2025 (1 yr 5 mo ago)
Description:
CSSP;CONST. /IMPROVEMENT OF ACCESS ROAD LEADING TO RAILWAYS STATIONS(KALSAD TUNGO SA PALIPARAN,RILES AT DAUNGAN PROGRAM-KATUPARAN)- ACCESS ROAD LEADING TO NAGA CITY PNR STATIONS NAGA CITY CAMARINES SUR
Category:
GAA 2025 CP
Implementing office:
Contractor:
CENTERWAYS CONSTRUCTION AND DEVELOPMENT INC. · DPWH contractor code 34105
Contract amount:
₱48,264,831.08 (₱48.3M)
Funding source:
Regular Infra - GAA 2025 CP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
061b9ccc788a…May 20, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 3RD₱48,264,900.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25FF0064Mar 19, 2026BIP;FLOOD MITIGATION STRUCTURE PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF REVETMENT ALONG YABU RIVER DEL ROSARIO NAGA CITY CAMARINES SUROn-Going₱141.1M
25FF0075Mar 19, 2026CONST OF RAINWATER COLLECTOR SYSTEM S1:DPWHSATELITE LAB BLDG CANAMAN S2:NORTHERN CANAMANHS FUNDADOCANAMAN S3:PONONG INT SCHOOL MAGARAO S4:MPB BALATASAN CALABANGA S5:MPB DOMINOROG CALABANGA S6:CONCEPCION FLLORIN NHS SAGURONG PILI S7:PAWILI ELEM SCHOOL PILICompleted₱2.6M
25FF0059Jan 23, 2026002;PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION /MAINTENANCE OF FLOOD MITIGATION STRUCTURE & DRAINAGE SYSTEM-CONST. OF REVETMENT ALONG PENAFRANCIA CREEK,UPSTREAM PALESTINA PILI CAMARINES SUROn-Going₱84.0M
25FF0042Nov 26, 2025BIP;ACCESS ROAD &/OR BRIDGES FROM THE NATL. ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES-CONST. OF ROAD AT ABELLA NAGA CITY CAMARINES SURCompleted₱4.9M
25F00072Jun 11, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K0439+000-K0440+650, NAGA CITY, CAMARINES SUR (3RD LEGISLATIVE DISTRICT)On-Going₱153.0M
25FF0038Jun 11, 2025CONST. (COMPLETION) OF MULTI PURPOSE BUILDING(COVERED COURT) BGY. TABUCO NAGA CITY CAMARINES SURCompleted₱3.0M
25FF0037Jun 5, 2025BIP;FLOOD MITIGATION STRUCTURE PROTECTING MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES-CONST. OF FLOOD MITIGATION STRUCTURE,CADENA DE AMOR TO CALLE TRESE,BAGUMBAYAN SUR NAGA CITY CAMARINES SUROn-Going₱9.7M
25FF0002Jun 3, 2025CONVERGENCE & SPECIAL SUPPORT PROG.-CONST./IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATION(TOURISM ROAD INFRASTRUCTURE PROG.-TRIP)ALMEDA HIGHWAY CONNECTING CENTRO HERITAGE DISTRICT TO MT. ISAROG NATURAL PARK NAGA CITY CAM SURCompleted₱4.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.