FY2026 GAA: ₱6.79T
PisoScan

Project 25FI0028

DPWH infrastructure contract
Contract ID:
25FI0028
Fingerprint:
091845aa93d92e…765a08ccd3 Verified
Status:
On-Going
Physical progress:
88.2%
Timeline:
Start Mar 4, 2025 (1 yr 8 mo ago)
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES - CONSTRUCTION OF ROAD BARANGAY BATUILA, BARANGAY BANASE AND BARANGAY
Category:
GAA 2025 SSP
Implementing office:
Contractor:
JRMG CONSTRUCTION AND SUPPLY · DPWH contractor code 44885
Contract amount:
₱9,698,001.69 (₱9.7M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
8a15efd27b14…Feb 18, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MASBATE 2ND DEO₱9,698,001.69

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26FI0027Aug 4, 2026ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - LAGTA-CROSSING MALINTA RD - K0099+520 - K0099+796, BALENO, MASBATEOn-Going₱29.6M
25FI0060Jan 9, 2026CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE /RAIN WATER COLLECTOR - WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BALENO, MASBATEOn-Going₱17.5M
25FI0041May 28, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - JCT. MILAGROS - BALENO - LAGTA RD (S00016MT) K0094+750 - K0094+783,On-Going₱36.9M
25FI0017Apr 2, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - LAGTA - CROSSING MALINTA RD (S00017MT) K0095+000 - K0095+115, BALENO,On-Going₱9.2M
25FI0020Mar 4, 2025ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BATUILA RIVER, BALENO, MACompleted₱85.0M
25FI0026Mar 4, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGE FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING FACILITIES - CONSTRUCTION OF ROAD, BARANGAY TINAPIAN AND BARANGAY DOCOL, BALENO,Completed₱9.7M
24FI0028Nov 25, 2024CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG LAGTA - CROSSING MALINTA RD. (S00017MT) - K0099+235 - K0099+550, BAOn-Going₱31.3M
24F00429Sep 27, 2024CAPITAL OUTLAY - DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP)-CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU-BALENO SUPER HEALTH CENTER, MASBATE, BALENO, MASBATE (2ND LEGISLATIVE DISTRICT)Completed₱11.9M