Project 25FM0051
DPWH infrastructure contract
Contract ID:
25FM0051
Fingerprint:
c1a16315a1931e…27331b7db0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 7, 2025 (1 yr 7 mo ago) · Target/actual end Aug 14, 2025
Description:
CONCRETING OF BRGY. RIZAL FMR, BRGY. RIZAL, BATUAN,MASBATE.
Category:
GAA 2025 DA FMR
Implementing office:
DPWH Masbate 1st DEO · Region V
Contractor:
SMDF CONSTRUCTION · DPWH contractor code 55026
Contract amount:
₱14,924,956.36 (₱14.9M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FM0054 | Jul 14, 2025 | CONVERGENCE PROGRAM - CONSTRUCTION/ REHABILITATION OF RAINWATER COLLECTORS IN PUBLIC FACILITIES - CONSTRUCTION/ REHABILITATION OF RAINWATER COLLECTORS SYSTEM (RWCS) IN PUBLIC FACILITIES. | Completed | ₱2.5M |
| 25FM0055 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BATUAN CENTRAL SCHOOL, BATUAN, MASBATE. | On-Going | ₱14.4M |
| 25FM0011 | Mar 27, 2025 | FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF SHORE PROTECTION STRUCTURE,BARANGAY DANAO, BATUAN, MASBATE. | Completed | ₱47.5M |
| 25FM0018 | Mar 27, 2025 | FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORE PROTECTION STRUCTURE, LAGUNDI, BARANGAY BURGOS, BATUAN, MASBATE. | On-Going | ₱47.5M |
| 25FM0042 | Mar 27, 2025 | FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY RIZAL, BATUAN, MASBATE | Completed | ₱26.0M |
| 25FM0007 | Feb 24, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - SUSTAINABLE INFRASTRUCTURE PROGRAM ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF ROAD, BARANGAY MABUHAY, BATUAN, MASBATE. | Completed | ₱12.5M |
| 24FM0042 | Apr 22, 2024 | CONCRETING OF BRGY. BURGOS TO BRGY. SAWANG FMR, BRGY. BURGOS, BATUAN, MASBATE. | Completed | ₱14.9M |
| 24FM0043 | Apr 22, 2024 | CONCRETING OF BRGY. ROYROY FMR, BRGY. ROYROY, BATUAN, MASBATE. | Completed | ₱14.9M |