DPWH infrastructure contract
Contract ID:
25G00051
Fingerprint:
68d8d137be4560…70e499e8d8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 18, 2025 (1 yr 7 mo ago) · Target/actual end Feb 23, 2026
Description:
CANDONI- GATUSLAO- BASAY BDRY. ROAD, NEGROS OCCIDENTAL
Category:
GAA 2025 OO-1
Implementing office:
DPWH Negros Island Region · Negros Island Region
Contractor:
H.L.J. CONSTRUCTION & ENTERPRISES · DPWH contractor code 18080
As listed: H.L.J CONSTRUCTION & ENTERPRISES
Contract amount:
₱101,009,715.03 (₱101.0M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
dbbff652ea57…Mar 6, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION VI₱101,010,126.25

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26RC0048Aug 17, 2026REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES - DAUG BR. (B00261NR) ALONG BACOLOD SOUTH RD (KABANKALAN-HINOBA-AN SECTION)On-Going₱6.7M
26RC0010Jun 22, 2026REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - BACOLOD SOUTH RD (KABANKALAN-HINOBA-AN SECTION) - K0183+314 - K0184+081On-Going₱17.0M
25RC0012Apr 20, 2026CONSTRUCTION OF 1 STY 2CL SCHOOL BUILDING, BULWANGAN NATIONAL HIGH SCHOOL, HINOBAAN, NEGROS OCCIDENTALOn-Going₱6.0M
24G00120Oct 31, 2024CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - HINOBAAN SUPER HEALTH CENTER, NEGROS OCCIDENTALCompleted₱11.9M
24GM0057Jun 20, 2024CONCRETING OF PUROK 7 TO PUROK 8, BRGY. CULIPAPA FMR, BRGY. CULIPAPA, HINOBA-AN, NEGROS OCCIDENTALCompleted₱14.9M
24GM0035Jun 11, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 1, POBLACION, HINOBA-AN, NEGROS OCCIDENTALCompleted₱17.8M
24GM0052May 6, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING HINOBA-AN, NEGROS OCCIDENTALCompleted₱9.9M
24GM0051Apr 11, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING-CONSTRUCTION OF MULTI-PURPOSE BUILDING IN THE MUNICIPALITY OF HINOBAAN, NEGROS OCCIDENTALCompleted₱5.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.