Project 25G00070
DPWH infrastructure contract
Contract ID:
25G00070
Fingerprint:
998b123665acaf…f60088e546 Verified
Status:
On-Going
Physical progress:
0%
Timeline:
Start Mar 18, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MINULU- AN RIVER (BOTHSTREAM) AT BACOLOD NORTH RD, TALISAY CITY, NEGROS OCCIDENTAL
Category:
GAA 2025 OO-2
Implementing office:
DPWH Negros Island Region · Negros Island Region
Contractor:
HOMEWORLD CONSTRUCTION CORP. (FORMERLY HOMEWORLD E · DPWH contractor code 14725
Contract amount:
₱179,682,935.50 (₱179.7M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26RA0125 | Jun 23, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BACOLOD NORTH RD - K0009 + 100 - K0009 + 520 | On-Going | ₱15.4M |
| 25RA0029 | Apr 8, 2026 | CONSTRUCTION OF FARM-TO-MILL ROAD, BARANGAY BAGTIC, SILAY CITY, NEGROS OCCIDENTAL | On-Going | ₱22.2M |
| 25RA0028 | Mar 25, 2026 | CONSTRUCTION OF FARM-TO-MILL ROAD, BARANGAY XVIII-A ROAD SECTION, VICTORIAS CITY, NEGROS OCCIDENTAL | On-Going | ₱24.8M |
| 25GK0097 | Jun 17, 2025 | CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD -BACOLOD NORTH RD - K0009 + (-273) -K0010+704 | On-Going | ₱24.2M |
| 25GK0021 | Jun 3, 2025 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG SILAY-LANTAWAN RD - K0039 + 200 - K0040 + 366 | On-Going | ₱13.6M |
| 25GK0125 | May 28, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. CONCEPCION, TALISAY CITY, NEGROS OCCIDENTAL | Completed | ₱6.8M |
| 25GK0127 | May 28, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. MATAB-ANG, TALISAY CITY, NEGROS OCCIDENTAL | Completed | ₱6.2M |
| 25GK0139 | May 28, 2025 | CONSTRUCTION OF ROAD AT SITIO BALOGO, BRGY. CONCEPCION, TALISAY CITY, NEGROS OCCIDENTAL | On-Going | ₱19.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.