Project 25GD0012
DPWH infrastructure contract
Contract ID:
25GD0012
Fingerprint:
fa5f28328662f1…84fd73df6f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2025 (1 yr 7 mo ago) · Target/actual end May 22, 2025
Description:
CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY TINIGBAN, PANITAN, CAPIZ
Category:
GAA 2025 SSP
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
SALMEGA BUILDERS · DPWH contractor code 45281
Contract amount:
₱7,328,475.00 (₱7.3M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GD0058 | Jun 23, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ROXAS CITY BDRY-PANITAN-BAILAN RD - K0112 + (-268) - K0113+ 434, K0116+606 - K0118+ 000, K0118+ 402 - K0118+920 | On-Going | ₱141.6M |
| 25GD0061 | Jun 17, 2025 | CONSTRUCTION OF CONCRETE ROAD, BARANGAY CABUGAO, PANITAN, CAPIZ | On-Going | ₱5.9M |
| 25GD0040 | Jun 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SALOCON, PANITAN, CAPIZ | On-Going | ₱4.9M |
| 25GD0043 | Jun 9, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - ROXAS CITY BDRY-PANITAN-BAILAN RD - KO113+470 - KO115+110 | On-Going | ₱35.7M |
| 25GD0054 | Jun 9, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MAAYON-JCT BAILAN RD - K0126 + 117 - K0129 + 000 | On-Going | ₱67.9M |
| 25GD0031 | Apr 14, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ROXAS CITY BDRY. PANITAN-BAILAN RD. - KO118+000 - KO118+402 | On-Going | ₱21.7M |
| 25GD0007 | Mar 24, 2025 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY BALATUCAN, PANITAN, CAPIZ | Completed | ₱4.9M |
| 25GD0021 | Mar 24, 2025 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - MAAYON-JCT BAILAN RD. - KO124+462 - KO124+529, KO124+559 - KO124+600, KO125+494 - KO125+559, KO126+050 - KO126+093, KO126+187 - KO126+253, KO126+681 - KO126+719 | Completed | ₱7.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.