Project 25GD0030
DPWH infrastructure contract
Contract ID:
25GD0030
Fingerprint:
f0cd475838c46d…c3f56aa0d1 Verified
Status:
On-Going
Physical progress:
97.9%
Timeline:
Start Apr 14, 2025 (1 yr 6 mo ago)
Description:
PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-ILOILO-CAPIZ RD. (NEW ROUTE) - KO114+830 -KO115+303
Category:
Roads
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
IBC INTERNATIONAL BUILDERS CORPORATION · DPWH contractor code 8576
Contract amount:
₱25,750,000.00 (₱25.8M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GD0056 | Jul 7, 2025 | CONSTRUCTION OF CONCRETE ROAD, BARANGAY MONGPONG, CITY OF ROXAS, CAPIZ | On-Going | ₱8.9M |
| 25GD0051 | Jun 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTA FE, PILAR, CAPIZ | On-Going | ₱4.8M |
| 25GD0048 | Jun 17, 2025 | CONSTRUCTION OF DPWH CAPIZ 1ST DEO OFFICE BUILDING, ROXAS CITY. CAPIZ | On-Going | ₱38.4M |
| 25GD0065 | Jun 17, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BALIJUAGAN,CITY OF ROXAS, CAPIZ | On-Going | ₱4.9M |
| 25GD0037 | Jun 9, 2025 | RECONSTRUCTION OF CONCRETE PAVEMENT - ILOILO CAPIZ RD (NEW ROUTE) - KO106+995 - KO107+570 | On-Going | ₱10.2M |
| 25GD0057 | Jun 9, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO-CAPIZ RD (NEW ROUTE) - K0116 + (-173) - K0116 + 100, K0116 + 400 - K0117 + 080 | On-Going | ₱35.8M |
| 25G00080 | May 21, 2025 | ROXAS CITY CIRCUMFERENTIAL ROAD, C2 SECTION, CAPIZ | On-Going | ₱86.4M |
| 25G00083 | May 21, 2025 | ROXAS CITY CIRCUMFERENTIAL ROAD, C3 SECTION, CAPIZ | On-Going | ₱43.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.