Project 25GF0102

DPWH infrastructure contract
Contract ID:
25GF0102
Fingerprint:
4d42f89bf64f5b…28493fb3aa Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 3, 2025 (1 yr 5 mo ago) · Target/actual end Oct 10, 2025
Description:
CONCRETING OF BRGY. OLO BARROC FMR, BRGY. OLO BARROC, TIGBAUAN, ILOILO
Category:
GAA 2025 DA FMR
Implementing office:
DPWH Iloilo 1st DEO · Region VI
Contractor:
ABRIGHT BUILDERS CORPORATION · DPWH contractor code 46487
Contract amount:
₱14,876,128.09 (₱14.9M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GF0118Oct 24, 2025CONSTRUCTION OF SCHOOL BUILDING, TIGBAUAN NATIONAL HIGH SCHOOL, TIGBAUAN, ILOILOOn-Going₱59.7M
25GF0096Jun 16, 2025CONSTRUCTION OF CORDOVA - BAROSONG BRIDGE, TIGBAUAN, ILOILOOn-Going₱48.1M
25GF0010Jun 3, 2025INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG ILOILO-ANTIQUE RD - K0021+000 - K0022+751On-Going₱9.7M
25GF0048Jun 3, 2025ROAD WIDENING- ILOILO-ANTIQUE RD -K0023+734 - K0023+757, K0023+912 - K0024+079, K0024+079 - K0024+123Completed₱8.8M
25GF0089Jun 3, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, TIGBAUAN, ILOILOOn-Going₱139.8M
25GF0101Jun 3, 2025CONCRETING OF BRGY. BITAS FMR, BRGY. BITAS, TIGBAUAN, ILOILOCompleted₱14.9M
25GF0103Jun 3, 2025CONCRETING OF SITIO HATOL TO SITIO KATIKLAN, BRGY. NANGA FMR, BRGY. NANGA, GUIMBAL, ILOILOOn-Going₱14.9M
25GF0066Apr 11, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, BARANGAY CORDOVA SUR, TIGBAUAN, ILOILOCompleted₱7.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.