Project 25GG0228
DPWH infrastructure contract
Contract ID:
25GG0228
Fingerprint:
b6c41a2f78b8c1…8786233b20 Verified
Status:
On-Going
Physical progress:
96.1%
Timeline:
Start Mar 27, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - BAROTAC NUEVO-DUMANGAS-DACUTAN WHARFV RD - K0274 + (-1004) - K0274 + (-531), K0283 + 428 - K0283 + 729
Category:
GAA 2025 OO-1
Implementing office:
DPWH Iloilo 2nd DEO · Region VI
Contractor:
HORTINELA CONSTRUCTION & SUPPLY · DPWH contractor code 38219
Contract amount:
₱15,855,390.10 (₱15.9M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26GG0042 | Jun 10, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BAROTAC NUEVO-DUMANGAS-DACUTAN WHARF RD - K0274 + (-1004) - K00274 + (-008) | On-Going | ₱28.4M |
| 26GG0047 | Jun 10, 2026 | CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - DUMANGAS-BAROTAC NUEVO DIVERSION ROAD, BARANGAY AGCUYAWAN CALSADA - BARANGAY AGCUYAWAN PULO, BAROTAC NUEVO, ILOILO - BARANGAY BOLILAO, DUMANGAS, ILOILO - STA. 0 + 000 - STA. 1 + 140 | On-Going | ₱34.2M |
| 26GG0059 | Jun 9, 2026 | ROAD WIDENING - ILOILO EAST COAST-CAPIZ RD - K0271 + 661 - K0272 + 898 | On-Going | ₱41.3M |
| 25GG0201 | May 21, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER IN BAROTAC NUEVO, ILOILO (PACKAGE B) | On-Going | ₱119.1M |
| 25GG0232 | May 21, 2025 | CONSTRUCTION OF SCHOOL BUILDING, PALACIAWAN ELEMENTARY SCHOOL, BAROTAC NUEVO, ILOILO | Completed | ₱6.4M |
| 25GG0234 | May 21, 2025 | CONSTRUCTION OF SCHOOL BUILDING, TINORI-AN ELEMENTARY SCHOOL, BAROTAC NUEVO, ILOILO | Completed | ₱6.5M |
| 25GG0235 | May 21, 2025 | CONSTRUCTION OF SCHOOL BUILDING, TUBUNGAN PRIMARY SCHOOL, BAROTAC NUEVO, ILOILO | Completed | ₱6.5M |
| 25GG0137 | Mar 25, 2025 | CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - BANGA BANTE - BANGA - POLOT-AN - BAROTAC NUEVO RD - K0275 + (-676) - K0275 + (-235) | Completed | ₱8.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.